Meeting Our Statutory Requirements<br />
Condition of Public Works (continued)<br />
Footpaths<br />
Based on the PMS data. Over 25% of the footpath network meeds some form of reconstruction to<br />
improve pedestrian safety. Using a design life of approximately 20 years, funding of 5% of the asset<br />
value is needed each year to maintain the condition of our footpath assets.<br />
Drainage<br />
Using the information collected as part of <strong>Waverley</strong>’s AAS 27 evaluation, we have over 70km of<br />
drainage assets of which only 50% are in a good condition. Based on a conservative estimate, 1.5%<br />
of the asset value is needed each year to maintain these assets.<br />
Urban Roads<br />
Regional Roads<br />
Kerb and Gutter<br />
Footpath<br />
Drainage<br />
Condition as at<br />
June 30, 2002<br />
<strong>Annual</strong> <strong>Report</strong> <strong>2005</strong>//<strong>2006</strong><br />
Estimate of cost to bring<br />
to satisfactory standard<br />
(current $ value)<br />
Estimate of cost to<br />
maintain standard<br />
(current $ value)<br />
Pavement rehabilitation and<br />
resealing works required<br />
Pavement rehabilitation and<br />
10,160,000 960,000<br />
resealing works required<br />
Reconstruction and repairs<br />
955,000 90,000<br />
required to improve road<br />
profile.<br />
Upgrading works required to<br />
3,465,000 605,000<br />
improve pedestrian safety<br />
and reduce Public Liability<br />
exposure.<br />
Works required to repair pipe<br />
5,950,000 880,000<br />
network and improve<br />
capacity of system.<br />
40,500,000 1,980,000<br />
Maintenance Program<br />
<strong>2005</strong>/<strong>2006</strong><br />
Total<br />
Urban Roads Minor maintenance $228,408<br />
Concrete Roads $121,164<br />
Local Roads Re-sheeting $1,187,557<br />
Regional<br />
Roads Regional Roads Re-sheeting $8,047 $1,545,176<br />
Kerb and<br />
Gutter Minor Repairs $91,619<br />
Pram Ramps $3,761<br />
Construction $370,194 $485,574<br />
Footpath Minor Repairs $343,194<br />
Construction $2,688,358 $3,031,552