154<br />

HEP ANNUAL REPORT 2010<br />

CHAPTER 7 - REPORTS BY HEP GROUP COMPANIES WITH FINANCIAL STATEMENTS<br />

HEP-OPERATOR<br />

DISTRIBUCIJSKOG SUSTAVA d.o.o.<br />

MIŠO JURKOVIΔ<br />

DIRECTOR<br />

HEP ODS (HEP Distribution System Operator) business operations in 2010 were aimed at meeting its legal role in<br />

the electricity market and achieving business objectives in accordance with HEP Group business policy. Improving<br />

operating cost efficiency continued and HEP d.d. Management Board decision concerning reduction in manageable<br />

and partly manageable costs was implemented. Great significance was given to the processes related to the functioning<br />

of the electricity market, primarily through improvement in IT support in the process of supplier switching<br />

and exchanging metering data.<br />

The trend of diminishing number of cases of ascertained unauthorized electricity consumption continued as a<br />

result of permanent activities to refurbish metering points. The continuous business objectives have been to improve<br />

payment collection, optimize inventories, raise the quality of electricity supply, and raise the quality of services in<br />

the activities of distribution and supply.<br />

During the year, 16 capital projects were successfully completed (of the voltage level 110 kV, 35 kV and 20 kV).<br />

Other investments were also fully carried out. Investments in the reconstruction of 110 kV transformer stations were<br />

completed: TS 110/10(20) kV Đakovo 3, TS 110/10(20) kV Dugo Selo, TS 110/10(20) kV Vrbovsko i TS 110/30/10(20)<br />

kV Podi. Also completed was construction or reconstruction of several 35 kV and 20 kV facilities: TS 35/10(20)kV<br />

Čakovec Istok, Sali, Park, Križ, Postira i Vrata; KB 20/35 kV Kostajnica – Dvor; KB 10(20) kV TS 110/35/10(20) kV<br />

Poreč – Poreč 1 – Poreč 2; PKB 20 kV Turanj – Babac – Pašman; DV 10(20) kV Kolan – Gajac; changeover to 20 kV in<br />

the Krapina area and additions to DC Vinkovci with equipment replacement.<br />

In 2010, procurement and installation of 1,000 remote-communication interval meters was carried out, which<br />

were incorporated in AMR (Automatic Meter Reading) system, whereby metering data necessary for the functioning<br />

of the electricity market were secured (determination of electricity consumption in hourly intervals). As part of the<br />

program of refurbishment of metering points, 871 hand-held terminal were procured with software support and a<br />

meter reading probe, for all distribution areas.<br />

In accordance with the pace of return of displaced persons and refugees, reconstruction continued in areas<br />

war affected areas.<br />

During 2010, the activities intensified to connect power plants which are in the renewable sources incentive<br />

system to the distribution network. In the preparatory part, analyses of connection possibilities and studies<br />

on optimum technical solutions encompassed 23 power plants of 80 MW of combined capacity and 16 preliminary<br />

connection approvals were issued for a total capacity of 61 MW. During 2010, six power plants of 14 MW in total<br />

were connected to the distribution network. Connecting power plants to the network raises questions about trial<br />

operation of power plants on the network, network operation with distributed generation and maintenance of the<br />

distribution network which is not radially supplied any more. We face numerous challenges, from coordination with<br />

HEP OPS through adoption of standards to recognition of distributed production which will increasingly affect the<br />

concept of development, operation and maintenance of the distribution system.<br />

The refurbishment cycle of medium-sized control centers aimed at establishing a state-of-the-art architecture<br />

of the electricity network remote control and monitoring system was completed. HEP ODS expert team initiated the<br />

development of SCADAinfo application for these centers, which makes it possible to access data from SCADA through<br />

the internet in HEP’s business network.<br />

A single base of remotely-read customer metering points above 30kW in connected load has been continuously<br />

expanding and now contains metering data from more than 15 thousand metering points. Also, investigations<br />

have been initiated to determine compensating load curves for particular customer categories that have meters<br />

without the possibility of storing energy data in a time interval. In 2010, a pilot project to install meters with remote<br />

switch- off was successfully implemented.