30.04.2014 Views

July (pdf) - New York Power Authority

July (pdf) - New York Power Authority

July (pdf) - New York Power Authority

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

east from the St. Lawrence Project to Plattsburgh, <strong>New</strong> <strong>York</strong>, and to the Vermont border; two 230-kV lines<br />

extending south from the St. Lawrence Project to Belfort, <strong>New</strong> <strong>York</strong>; a single circuit underground and<br />

underwater line extending across Long Island Sound between Con Edison’s substation in Westchester County<br />

and LIPA’s substation in Nassau County, <strong>New</strong> <strong>York</strong>; several 115-kV lines connected directly to large<br />

industrial customers and other shorter lines connecting the <strong>Authority</strong>’s generating facilities to the transmission<br />

grid.<br />

In 2003, the <strong>Authority</strong> completed construction of a transmission control device known as the<br />

Convertible Static Compensator at its Marcy substation. This technology provides voltage control and helps<br />

reduce congestion on heavily used transmission lines between Utica and Albany, <strong>New</strong> <strong>York</strong>.<br />

Long Island Sound Cable<br />

The Cable consists of a 345-kV underground and underwater transmission cable, extending for<br />

approximately 26.6 miles from the Sprain Brook substation owned by Con Edison in Westchester County,<br />

<strong>New</strong> <strong>York</strong>, to the East Garden City substation owned by LIPA in Nassau County, <strong>New</strong> <strong>York</strong>, and includes<br />

an underwater crossing of approximately 7.9 miles of Long Island Sound. Installation of the Cable was<br />

completed in 1991.<br />

Tri-Lakes Transmission Reinforcement Project<br />

In September 2004, the <strong>Authority</strong>, National Grid, and the Villages of Tupper Lake and Lake Placid<br />

executed a settlement agreement designed to settle a dispute relating to cost responsibility for certain<br />

transmission system upgrades. Under the settlement agreement, National Grid is responsible for the<br />

construction of substation equipment and a new overhead line to alleviate serious transmission capacity<br />

deficiencies in the Lake Placid, Tupper Lake and Saranac Lake, <strong>New</strong> <strong>York</strong>, area of the Adirondacks. The<br />

upgrades consist of (a) one 46-kV Static Var Compensator (‘‘SVC’’) at Tupper Lake and one 115-kV SVC at<br />

Lake Colby (collectively, the ‘‘SVCs’’); and (b) a new overhead 46-kV line from Stark/Townline substation<br />

to a new regulator station at Piercefield (the ‘‘<strong>New</strong> Line’’) (collectively, the ‘‘Tri-Lakes Project’’).<br />

National Grid is responsible for the design, engineering, procurement, construction, installation,<br />

testing, and overall project management for the Tri-Lakes Project, subject to oversight by the <strong>Authority</strong>. The<br />

<strong>Authority</strong> was the applicant for governmental permits or approvals required for the siting or construction of<br />

the <strong>New</strong> Line, and National Grid was the applicant for permits or approvals required for the SVCs. The<br />

SVCs were placed into service in 2007 and the <strong>New</strong> Line entered into service in May 2009. The<br />

settlement agreement contemplated that the <strong>Authority</strong> would own and finance the Tri-Lakes Project up to<br />

January 1, 2012, at which time the Tri-Lakes Project would be transferred to National Grid upon payment of<br />

the Net Project Cost, as defined below. The parties are considering advancing the transfer date.<br />

The current cost estimate for the Tri-Lakes Project is $52.9 million (‘‘Total Project Cost’’). The Net<br />

Project Cost shall equal the Total Project Cost less $9.7 million (in 2004 dollars), which is the portion of the<br />

Tri-Lakes Project cost borne by Tupper Lake ($3.2 million) and Lake Placid ($6.5 million). The <strong>Authority</strong><br />

will finance both National Grid’s and the Villages’ share of the Total Project Cost but will be reimbursed<br />

for these costs. The <strong>Authority</strong> and National Grid will share equally in any cost increases above the<br />

estimated cost of the transmission line part of the Project (estimated to cost $15.8 million in 2004 dollars).<br />

The <strong>Authority</strong>’s share of cost increases is estimated to be less than $10 million.<br />

Certain Operating Information<br />

Effective in 1965, the <strong>Authority</strong> and Ontario Hydro entered into a Memorandum of Understanding<br />

containing provisions for coordinated operation of the two systems, for interchange of power and energy at<br />

2-39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!