20091231-0037 FERC PDF (Unofficia1) 12/29/2009<br />

Direct Testimony of Alan C. Heintz<br />

Docket ER 10- -000<br />

Page 23 of28<br />

Exhibit No. SCE-8<br />

2009 actual costs and investment. Differences. if any, between the ATRR estimate<br />

2<br />

3<br />

initially calculated and that ATRR based on actual cost will be handled as a true-up<br />

adjustment (pro-rated for the number of days the rate was in effect for the initial period).<br />

4 Q.<br />

5<br />

PLEASE EXPLAIN THE ESTIMATE AND TRUE-UP MECHANICS OF THE<br />

FORMULA_<br />

6 A.<br />

The true-up mechanics are set out as protocols in Attachment H, Appendix B.<br />

The<br />

7<br />

calculation of the true-up with interest is accomplished on Attachment 6 -- Estimate and<br />

8<br />

True-up Worksheet.<br />

Each May beginning in 2010, SCE&G will complete the formula<br />

9<br />

using the data contained in the prior calendar year's FERC Form I and will prepare the<br />

10<br />

cost support schedules contained in the formula.<br />

The estimated ATRR in effect prior to<br />

II<br />

June 1, 2010 will first be adjusted by multiplying it by the ratio of the current year 12 CP<br />

12<br />

divided by the prior year 12 CPo<br />

This adjustment compensates for any growth (or<br />

13<br />

decrease) in billing determinants that occurred during the <strong>Rate</strong> Year.<br />

(See Step 9 on<br />

14<br />

IS<br />

Attachment 6.) The adjusted prior year ATRR is then subtracted from the ATRR<br />

calculation using actual costs for 2009, and the difference (with interest) will be added to<br />

16<br />

17<br />

(subtracted from) the estimated ATRR that will be effective on June 1, 2010.<br />

process will be repeated each year subsequent to 2010.<br />

This<br />

18<br />

The formula templates, exhibits and cost support will be posted on SCE&G's website.<br />

19<br />

Consistent with the Commission's<br />

recent Duquesne order, SCE&G will also make an<br />

20<br />

informational filing at FERC.<br />

Thus, the Commission and SCE&G's customers have an<br />

21<br />

22<br />

opportunity to review the formula calculations and supporting data before the changes<br />

take effect, and to challenge the rate recalculations.