Site 2<br />

Consists of 50-acres located in the south-central region of the tract almost exclusively in Section<br />

13 Township 25 Range 18. The dominant soils are Adamsville and Smyrna fine sands, with<br />

smaller pockets of Sellers mucky loamy fine sand, Cassia fine sands, and Narcossee fine sands<br />

(National Cooperative Soil Survey 1982).<br />

Site 2 will be restored in 2008 using a combination of direct seeding and plant installation<br />

(Figure 7). Site preparation will begin 1-2 years in advance of seeding with 2-3 aerial herbicide<br />

applications per year to effectively reduce bahia grass, accompanied by one or two disking<br />

treatments. If introduced grasses (bahia, Bermuda, cogon, natal) are sufficiently eradicated, the<br />

site may be allowed to lie fallow the summer prior to seeding to provide a firmly packed<br />

seedbed, facilitate full recharge of soil moisture profile, enhance nutrient availability, and to<br />

reduce recruitment of undesirable weeds. The site will be burned in February 2008, followed by<br />

several aerial applications of either Roundup or AquaStar herbicide, and another burn, if<br />

feasible. Disking and rolling requirements will be based on the results of the 2006 and 2007<br />

seeding events and site conditions. In November 2008, seeding will be conducted on the entire<br />

50-acres, followed by installation of primarily wiregrass on approximately 8-acres around the<br />

perimeter and westernmost portion of the site. An aerial application of Plateau may be applied<br />

at a rate of 12 ounces per acre 4-5 months after seeding to reduce survival of bahia grass<br />

seedlings. Installation of longleaf pine will be conducted on the site after success criteria are<br />

achieved.<br />

Figure 8. Conner Preserve Upland Restoration Site 3.<br />

16<br />

326