Land Acquisition & Associated Preservation <strong>Mitigation</strong> Credits – June, 2006<br />

Site Evaluation & Develop Conceptual <strong>Plan</strong> – 2006-2010<br />

Phase I - Wetland Restoration (Marsh) (Figure C - Hillsborough Basin) – Construction & <strong>Plan</strong>ting – 2010-<strong>2012</strong><br />

Maintenance & Monitoring - 3 years minimum – <strong>2012</strong> - 2014<br />

Colt Creek Floodplain (Forested Wetland) (Figure E - Withlacoochee Basin) – Const. & <strong>Plan</strong>ting – 2010-<br />

<strong>2012</strong><br />

Maintenance & Monitoring – 5 years minimum – 2011-2016<br />

Phase II - <strong>Water</strong>shed Modeling – 2010-2011<br />

Wetland Hydrologic Restoration - Design & Permitting – <strong>2012</strong><br />

Wetland Enhancement Construction – Hills. & Withlacoochee Basins – <strong>2012</strong>-2013 (Figures C, F)<br />

Maintenance & Monitoring (Minimum five years) - 2013 – 2018<br />

Project cost: $9.9 million (total)<br />

Acquisition - $7,560,000<br />

<strong>Water</strong>shed Modeling, Design, Permitting - $250,000<br />

Wetland Restoration & Enhancement - $900,000<br />

Upland Restoration & Enhancement - $790,000<br />

Post-Construction Maintenance & Monitoring - $400,000<br />

ATTACHMENTS<br />

1. Description of existing site and proposed work. Previous discussion & Attachment A – Existing Site &<br />

Proposed Activities<br />

2. Aerial photographs. Figures A-F, 2009 aerials.<br />

3. Location map and figures of existing and proposed conditions. Figure A – Location Map, Figure B –<br />

<strong>Water</strong>shed Boundaries, Figures C-F – Existing & Proposed Habitat Improvements.<br />

4. Schedule for work implementation, including any and all phases. The work schedule for proposed activities<br />

presented under Project Implementation.<br />

5. Success criteria and associated maintenance & monitoring plan. Refer to Attachment B – Maintenance &<br />

Monitoring <strong>Plan</strong>, Success Criteria.<br />