69<br />
Using the Internet site of ARC as a template for this application was an excellent<br />
decision. The pull-down menu system allowed for restricted access to different modules<br />
based on a user’s roles, and the layout was well received by both the users and<br />
management at ARC.<br />
One of the most notable areas where the project did not go as planned was in the<br />
communication between this author and ARC regarding deadlines. A project plan was<br />
developed so that specific modules would be designed on a schedule. The problem was<br />
getting ARC to dedicate the staff needed to thoroughly test these modules and to report<br />
any bugs that were found. By not allocating proper resources in terms of personnel to the<br />
testing of the project, ARC increased the risk of not having the application developed in<br />
the timeframe they wanted.<br />
Another area where the project went wrong was in failing to thoroughly test the<br />
speed of the application at its maximum usage. Having failed to do this the application<br />
began to slow a few months following implementation. ARC was not willing to put the<br />
application through aggressive testing due to the urgency of implementing it into the<br />
production environment. Their thought was to allow users to do performance testing in<br />
the production environment and then revisit any issues that may arise. Final testing of an<br />
application in the production environment is not the suggested way of performing stress<br />
testing.<br />
Project variables and their impact on the project:<br />
The most significant variable that impacted this project was the speed of the<br />
application after it was deployed to the production environment and in use by hundreds of