SOUND IMPLEMENTATION AND MAINTENANCE STRATEGIES/ACTIVITIES<br />
implementation and after the awarding of the CBFMA damaging at<br />
least 423.43 hectares of the established plantation with damage cost<br />
estimated at P2,248,888.21. This manifests the PO’s incapability to<br />
protect the project from forest fires due, among others, from slash and<br />
burn agriculture or kaingin system and ant egg collection.<br />
Despite the PO’s apparent incapability to protect the project from forest<br />
fires, maintenance and protection contract costing P750,000 was still<br />
awarded to DMADAI on February 18, 2004. The maintenance contract<br />
should not have been awarded in the first place as the area is covered<br />
by a CBFMA. As discussed earlier, under the CBFMA, the PO is<br />
responsible in maintaining and protecting the area at its own expense<br />
after two years upon completion of CSD contract.<br />
As reflected in the Work and Financial Plan, the contracted activities<br />
were supposed to be undertaken from February to June 2004.<br />
Evaluation of the POs accomplishments from June to August 2004,<br />
however, revealed that several contracted activities were not undertaken<br />
as illustrated below:<br />
Activities Target Cost<br />
Accomplishments<br />
Physical /<br />
Amount<br />
Nursery Operation– 303,120<br />
seedling production seedlings<br />
Plantation Protection<br />
& maintenance<br />
Banana sucker 1,200 24,000.00 1,200/<br />
P24,000<br />
P227,340.00 0 Due to long drought<br />
Fireline maintenance 407 172,975.00 0<br />
Patrol works 1,263 285,564.30 2,037.02 /<br />
P249,939.50<br />
Remarks<br />
Delayed implementation. Implemented<br />
from July to August 2004 only.<br />
Fire occurred on the following dates<br />
caused by adjacent kaingin damaging<br />
Gmelina Plantation at site:<br />
Proj. Mngt Cost 1,710 40,000.00 0<br />
Total<br />
P749,879.30 P301,517.44<br />
Date Site Value<br />
3/13/04 Dumayop P 303,239.72<br />
3/17/04 Tabban 339,532.25<br />
6/20/04 Dumayop & 930,867.07<br />
Baretet<br />
Total<br />
P1,573,639.04<br />
Despite the PO’s delay and failure to accomplish some activities under<br />
this contract, the contract was still extended until December 30, 2004<br />
with additional funding of P448,325 to cover additional activities. The<br />
implementation of additional activities which were supposed to be<br />
completed by December 2004 was also delayed as tabulated in the next<br />
page:<br />
63