Work Health and Safety (WHS)<br />
Ovals<br />
44. Further work continuing on WHS Safe Work Instructions and Inspection forms with<br />
asset services staff completing on the job Take 5 risk assessments.<br />
45. No significant works or issues to report.<br />
Parks & Gardens<br />
46. Ongoing maintenance works on reserves carried out.<br />
Private Works<br />
47. Reinstatement works done for <strong>SA</strong> Water in Kingscote and Penneshaw.<br />
Project Management<br />
48. DPTI Renewal of Unsealed Roads Stage 2:<br />
a. All works complete with project entering defects liability.<br />
49. DPTI Renewal of Unsealed Roads Stage 3:<br />
a. Hickmans Road & Wedgewood Road project scoping underway.<br />
b. Ironstone Rubble samples collected from known sources of pit material, for<br />
grading & testing, and inclusion in tender documents.<br />
c. Vegetation clearance to be reviewed with Native Vegetation <strong>Council</strong>. “Eastern<br />
Ring Route” being scoped for assessment and potential project costing estimate.<br />
50. Kingscote Streets upgrade - Completed and in Defects Liability period for 12 months.<br />
51. Kingscote Town Hall Fire protection - Detection System works completed and<br />
commissioned by CFS. Staff trained in operation of the Control panel. Awaiting<br />
delivery and installation of tank, delayed due to rain; expected completion early July.<br />
52. Kingscote Town Hall Façade upgrade - Project will carry forward due to timing of<br />
ensuring Heritage requirements are met.<br />
53. Street Designs - Parndana, American River & Kingscote. Design phase near<br />
completion and project costing to follow in FY13/14.<br />
54. Stokes Bay Road - LGTAP have received <strong>Council</strong>’s application. Awaiting decision;<br />
Traffic Engineer advice sought with regard to establishment of an 80 km/h speed zone<br />
and likely impacts. Report to be tendered once LGTAP funding levels are known.<br />
Assessment being undertaken on potential cost savings from overall HDS Audit.<br />
55. Depot Office Accommodation - Buildings arrived and installed 3-5 June, associated<br />
trades have completed works, awaiting fit out. Expect to occupy 2 nd week of July.<br />
56. Boating Facilities:<br />
a. Christmas Cove Car & Trailer parking project - Resubmitted to <strong>SA</strong>BFAC in April.<br />
Awaiting decision from the July <strong>SA</strong>BFAC Meeting.<br />
b. American River Breakwater extension - Project has been submitted to<br />
Development Assessment Commission, and <strong>SA</strong>BFAC (meeting in July)<br />
c. Bay of Shoals Tender Pontoon - Project referred to Development Services<br />
department from Development Assessment Commission. Referrals to EPA &<br />
Coastal Protection Board of DEWNR ongoing. Awaiting prudential review of<br />
Request for Information (RFI) document from legal adviser prior to seeking RFI<br />
period.<br />
d. Emu Bay Boatramp Upgrade - Project has been submitted to <strong>SA</strong>BFAC for the July<br />
meeting.<br />
<strong>Kangaroo</strong> <strong>Island</strong> <strong>Council</strong> – 10 July 2013 <strong>Agenda</strong> 70