Council Agenda - Kangaroo Island Council - SA.Gov.au
Council Agenda - Kangaroo Island Council - SA.Gov.au
Council Agenda - Kangaroo Island Council - SA.Gov.au
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Question 2:<br />
Given <strong>Council</strong> was briefed at the May 2012 workshop by its engineers through a ‘power<br />
point’ presentation, of the consequences and risks associated with a dam (detailed within<br />
Sheets C08 & C11) being sited at the end of Cheopis Street, on what basis was this site<br />
chosen in preference to the recommended location on the top of Binneys Track shown on<br />
2008 Layout<br />
Plan: (http://www.kangarooisland.sa.gov.<strong>au</strong>/webdata/resources/files/Penneshaw-CWMS-<br />
Scheme_Layout-2008-August.pdf ) and other alternative sites identified by the consultant<br />
Answer<br />
The site was preferred by <strong>Council</strong>lors as it represented a compromise between the costs<br />
associated with the original Binneys Track proposal (the issue of vertical lift and the<br />
ongoing high costs of pumping effluent up to this site were raised by <strong>Council</strong>lors during the<br />
early assessments). The other alternative site to the south of the Golf Course has issues in<br />
terms of visual amenity, cost of land, proximity to watercourse etc. A report in the July<br />
<strong>Agenda</strong> discusses this further.<br />
Question 3:<br />
Have the risks of siting an earth dam on land above and close to the residential area and<br />
issues related to earthquake-induced liquefaction (which is a common c<strong>au</strong>se of earth dam<br />
failure) been taken into consideration and factored in the designs and the construction<br />
costs of the dam shown on Drawings-Sheets C08 & C11 If so, why does <strong>Council</strong> need to<br />
conduct a further assessment on the designs and analysis of dam break risks<br />
Answer<br />
Yes it has – our Engineers would not have suggested the site and the design if they had<br />
not assessed these issues as being minimal. They have made it clear that detail design<br />
work would formally address any risk associated with the topography, tectonic, precipitation<br />
activity and other land based parameters. However, there have been repeated suggestions<br />
implying that a lagoon in this location would present major issues despite no facts being<br />
made available to substantiate this. We have maintained that once the facts are<br />
established, these perceived risks will either be validated or dismissed. <strong>Council</strong> will make<br />
its own assessment of the advice it receives and will resolve whether to proceed with this<br />
site or not at this time.<br />
Given the repeated suggestions implying that the design is in some way unsuitable,<br />
<strong>Council</strong> determined in April to formally request that this work be carried out in order to bring<br />
facts to the fore as soon as possible.<br />
Question 4:<br />
If the matter in ‘Question 3' above was overlooked, why should this <strong>Council</strong> need to pay<br />
extra consultant fees for further advice on the ‘probabilities of damage to an earth wall due<br />
to earthquakes’ as directed by <strong>Council</strong> in ‘Resolution 20.1’ of April 2013 meeting <br />
Answer<br />
As above. Due to the continued suggestions implying the design is unsuitable <strong>Council</strong><br />
determined to specifically request additional work be done before the rest of the project is<br />
completed. At this stage we have not been informed whether this work will attract additional<br />
fees or otherwise.<br />
<strong>Kangaroo</strong> <strong>Island</strong> <strong>Council</strong> – 10 July 2013 <strong>Agenda</strong> 6