<strong>Interim</strong> Report, No 3, 19 <strong>September</strong> <strong>2011</strong> – 18 <strong>March</strong> 2012<br />

2.10 Working Group 3. Cross-border Cooperation and Multilateral Environmental<br />

Agreements<br />

Activity 3.1 Nature Protection Sub-group<br />

Implemented activities during the third interim <strong>report</strong>ing period<br />

• Preparation and delivery of Module 3 regional workshop: “Communication Strategies with<br />

Stakeholders”, Djerdap, Kladovo, Serbia (1 – 3 November <strong>2011</strong>). The agenda items were the<br />

following:<br />

1. Aarhus and public participation; objectives of Communication;<br />

2. Work with Stakeholders: identifying; involving; informing;<br />

3. Do’s and Don’ts in involving the public; use of Communication media e.g. press; radio;<br />

publications; meetings etc.;<br />

4. Good practice case studies.<br />

For more details please see the enclosed workshop <strong>report</strong> (Annex 15).<br />

• Delivery of the 2 nd Annual Meeting of WG 3 Nature Sub-group Coordinators. The meeting<br />

was <strong>org</strong>anised in Podgorica, Montenegro (15 December <strong>2011</strong>).<br />

The main objective of the meeting was to present the implemented activities since the 1 st Annual<br />

Meeting and to reach the agreement on the planned activities in the upcoming period (confirmation<br />

of the selected topics, dates and venues).<br />

Planned activities for the next interim <strong>report</strong>ing period<br />

• Preparation and delivery of the Module 4 Workshop “Module 4: Conducting Nature Impact<br />

Assessments”, due in the period 15 – 17 May 2012 in Shara. Kosovo under UNSCR 1244/99.<br />

A fact finding mission to the workshop venue area (Shara) is planned in April 2012 to discuss<br />

the workshop items and to identify the main local stakeholders.<br />

• Preparation and delivery of the Module 5: Developing sound Nature project proposals for<br />

donor consideration (Nature project development), due in 10 – 12 July 2012 in Durmitor NP<br />

(Montenegro).<br />

• Preparation and delivery of the Module 6: Monitoring Nature Protection Areas due in <strong>September</strong><br />

2012 in Tara NP (Serbia).<br />

Activity 3.2 Water Management Sub-group<br />

Implemented activities during the third interim <strong>report</strong>ing period<br />

• Delivery of the second regional training/workshop “River Basin District characterisation,<br />

including economic analysis”. In accordance with the work plan, the workshop has been<br />

<strong>org</strong>anised as back to back event together with Drin Dialogue meeting in Podgorica,<br />

Montenegro (26 – 27 <strong>September</strong> <strong>2011</strong>).<br />

The workshop was <strong>org</strong>anised in cooperation with Drin Dialogue. The training covered River Basin<br />

District characterisation stage, including water bodies’ delineation, pressures and impacts analysis<br />

and economic analysis, as required by the WFD. As the training was held in the Drin river basin, it<br />

Human Dynamics Consortium 30