Remark: 1 Procurement Phase Cost – Costs <strong>of</strong> Major Equipment including process and<br />
mechanical equipment, construction equipment left on site and used after<br />
commissioning (see table p.13) and modules fabricated <strong>of</strong>fsite.<br />
2 <strong>Construction</strong> Cost – See “Instructions for <strong>Construction</strong> Direct and Indirect<br />
Costs” below.<br />
<strong>Construction</strong> Direct and Indirect Cost<br />
Direct costs are those which are readily or directly attributed to, or become an identifiable<br />
part <strong>of</strong>, the final project (e.g., piping labour and material). Indirect costs are costs that cannot<br />
be attributed readily to a part <strong>of</strong> the final product (e.g. temporary facilities).<br />
Please use the following table as a guide in categorizing direct and indirect construction cost.<br />
Direct <strong>Construction</strong> Cost<br />
Direct labour<br />
- See construction productivity table<br />
Direct subcontracts<br />
Bulk materials<br />
- See bulk material table<br />
<strong>Construction</strong> equipment (rental/ ownership<br />
& consumerables- fuel, oil, etc.)<br />
Indirect <strong>Construction</strong> Cost<br />
Indirect labour<br />
- See construction productivity table<br />
Labour burdens and Fringe benefits<br />
Overtime premium (additional cost for which no<br />
work is performed)<br />
Mobilization, Demobilization<br />
<strong>Construction</strong> <strong>of</strong>fice trailers and equipment.<br />
<strong>Construction</strong> utilities (power, water etc.)<br />
Temporary construction facilities (e.g. roads,<br />
fencing, fab. shops, etc.)<br />
Other consumables- small tools, supplies<br />
Scaffolding materials (rental/ ownership)<br />
Field services<br />
Permits (construction related)<br />
Vendor representatives<br />
Freight (for items listed in this table)<br />
Catering, accommodations<br />
Travel<br />
Misc. (insurance, etc.)<br />
Indirect subcontracts<br />
Note: For benchmarking purposes exclude the following:<br />
- Demolition cost<br />
- Remediation cost<br />
- Site preparation cost (construction cost begins with excavation for foundations or<br />
driving <strong>of</strong> piles)<br />
Provide data for <strong>Construction</strong> subtotal if indirect and indirect breakout is not available.<br />