3.6 Equipment<br />
Instructions<br />
Please complete the following tables indicating quantity and engineering work-hours for the<br />
categories appropriate to your project. If you cannot enter all data then enter totals only. Include<br />
rework in the work-hours only. If the project had no work-hours or quantities for a category,<br />
enter none.<br />
The Total Quantity <strong>of</strong> equipment is the amount <strong>of</strong> tagged items provided in the final Issued for<br />
<strong>Construction</strong> (IFC) drawings with vendor designed skids being counted as a single item. The<br />
Individually Designed quantity is the quantity defined by unique data sheets. For example, pump<br />
P201a/b is one unique data sheet, but is a total <strong>of</strong> two items.<br />
These hours include only mechanical discipline hours.<br />
Refer to the section “Instructions for Computation <strong>of</strong> Work-Hours and Rework-Hours” for an<br />
additional detailed listing <strong>of</strong> direct hours to be included and indirect hours that are to be excluded<br />
from the computation <strong>of</strong> the work-hours.<br />
Which design platform was used for this category in this project? Check all that apply.<br />
2D ( )<br />
3D ( )<br />
Pressure Vessels<br />
None<br />
Individually<br />
Designed<br />
(each)<br />
Total<br />
Quantity<br />
(each)<br />
Engineering WH<br />
(including rework)<br />
(hours)<br />
This includes tray/packed towers, columns, reactors/regenerators, and miscellaneous other<br />
pressure vessels.<br />
Field fabricated towers, columns, reactors and regenerators are to be included.<br />
Atmospheric Tanks<br />
None<br />
Individually<br />
Designed<br />
(each)<br />
Total<br />
Quantity<br />
(each)<br />
Engineering WH<br />
(including rework)<br />
(hours)<br />
This includes storage tanks, floating ro<strong>of</strong> tanks, bins/hoppers/silos/cyclones, cryogenic & low<br />
temperature tanks and miscellaneous other atmospheric tanks.<br />
Heat Transfer<br />
Equipment<br />
None<br />
Individually<br />
Designed<br />
(each)<br />
Total<br />
Quantity<br />
(each)<br />
Engineering WH<br />
(including rework)<br />
(hours)<br />
This includes heat exchangers, fin fan coolers, evaporators, cooling towers and<br />
miscellaneous other heat transfer equipment.<br />
26