1.1 IntroductIon<br />
TRIP REPORT<br />
USAID/ENI retained Bums and Roe Enterpnses, Inc. (BREI) to perform plant audit VISItS to<br />
seven Ukralman Thermal Power Plants (TES).<br />
The objective of these audit visits IS to improve the combustlOn efficIency of the UkraInian<br />
Power Plants.<br />
Burns and roe performed the plant audit visits dunng a Feb 6--Mar 11 trip to the UkraIne In<br />
accordance with the Delivery Order objectives. The folloWIng report describes the actiVIties of<br />
Team #2 (John E. Hallberg, P.E. and Prem Gupta), which visited Odessa CHP plant,<br />
Simferopol CHP plant, Krivoi Rog TPP and Burshtyn TPP. A report descnbmg the activities<br />
of Team #1 (Selisett Corban, P.E. and George Keller, P.E.) WhICh visited Kourakhovska,<br />
Uglegorsk and ZmIev TES was issued separately.<br />
1.2 Work Plan<br />
The follOWIng work was planned for each plant audit VISIt:<br />
• Perform introduction and information exchange wIth the plant management.<br />
• Discuss and present scope of the work.<br />
• Identify personnel to be assigned for hands-on audit training.<br />
• Provide traIning and assistance to the team selected for the use of the<br />
demonstration portable InstrumentatlOn.<br />
• Perform audit tests.<br />
• Turn over the demonstration portable instrumentation to the plant management<br />
and sign the papers.<br />
• Determine best location for installing stationary instruments.<br />
• • Determine best location for Installing receIver Instruments.<br />
• Define process and environmental condltlOnS as well as length of the cable runs.<br />
•<br />
•<br />