BURSHTYN<br />

COAL QUALITY<br />

The quality of the coal shipped to the power station was determined by analyses of<br />

samples taken manually from the railway cars. Quality of the coal fed to the furnace<br />

was determined by analyses of samples taken automatically before the conveyor belts<br />

of the bunker gallery.<br />

Average annual ash mOisture and heat values of the burned coal were as follows:<br />

1993 42.1% 9.9% 3294 kcal/kg<br />

1994 39.7% 8.7% 3679 kcal/kg<br />

The heat value of coal in 1994 comparing to that in 1993 increased due to lessening<br />

of coal slime, the Promproduct coal, and Donbass high-ash coal supply. At the same<br />

time, shipment of higher heat value coal from Western Donbass region increased. In<br />

1994 the quality of 22% of the coal received by the power plant dUring the year was<br />

checked. Actual ash content in the coal turned out to be 2.4% higher than that put<br />

In the attached quality certificates. At some deliveries the disparity reached 19-20%.<br />

In the 4th quarter the mine "Zakhldnodonbasska" drastically worsened the quality of<br />

Its coal. The disparity concerning ash content raised to 6-8%. During the year 1994,<br />

66 claims were made for Inadequate coal quality. The total price of the claims was<br />

2565.7 min. krb. (for 34591 tons of coal). 59 claims with the total price of 2037.9<br />

min. krb. (for 34469 tons of coal) were met. 22 claims which total price is 541.8<br />

min. krb. (for 10275 tons of coal) are under consideration.<br />

During the last year 147 claims were made for failure in performing of obligations for<br />

coal supply. The total price of the claims was 756.4 min. krb. (for 4402 tons of coal).<br />

85 of these claims with the total price of 360.4 min. krb. for 3083 tons of coal were<br />

satisfied. 8 claims with the total price of 38.3 min. krb. (for 226 tons of coal) were<br />

declined. 54 claims with the total price of 357.7 min. krb. (for 1093 tons of coal) are<br />

under consideration.<br />

DUring the last year 63 claims with the total price of 2854.2 min. krb. were made for<br />

late fuel delivery. 50 of these claims with the total price of 1365 min. krb. were<br />

conSidered and satisfied. The mentioned amount ofmoney was not transferred to the<br />

account of Burshtyn Power Plant due to shortage of funds at the account of the<br />

Directorate of L'vlv Railroads. (The payment orders are in the card index file.) DUring<br />

the last year 349.3 min. krb. was received for the claims carried-over from 1993 for<br />

late fuel delivery. 13 claims With the total amount of 1489.2 min. krb. are under<br />

consideration.