Management Discussion and Analysis<br />
Table 2. UHG mining license JORC (2012) compliant Coal Resource estimate, by depth and category, as at 30<br />
November 2015 (Note):<br />
Total Coal Resource<br />
Resource Category (Mt)<br />
Depth limit from topographic surface Measured Indicated Inferred<br />
Total<br />
(M+I)<br />
Total<br />
(M+I+I)<br />
Subcrop to Base Horizon of<br />
Weathering Elevation (“BHWE”) 2 3 5 5 10<br />
BHWE to 100m 73 23 17 97 114<br />
From 100m to 200m 94 48 26 141 168<br />
From 200m to 300m 91 64 21 155 176<br />
From 300m to 400m 57 35 15 92 108<br />
Below 400m 40 44 30 84 114<br />
Sub-Total above 300m 260 138 70 398 468<br />
Sub-Total below 300m 97 79 45 177 222<br />
Total 357 217 115 575 689<br />
Total (Rounded) 360 220 120 580 690<br />
Notes:<br />
(i)<br />
(ii)<br />
(iii)<br />
Technical information in the UHG Coal Resource estimation report has been compiled by Mr. Lkhagva-Ochir Said,<br />
General Manager of Technical Services, Mongolian Mining Corporation. Mr. Said is a member of the Australasian Institute<br />
of Mining and Metallurgy (Member #316005) and has over 8 years of experience relevant to the style and type of coal<br />
deposit under consideration and to the activity which is being undertaken to qualify as a Competent Person as defined<br />
by the Australasian Code for Reporting of Exploration Results, Minerals Resources and Ore Reserves, The JORC Code<br />
(2012). Mr. Said consents to the inclusion in the release of the matters based on this information in the form and context<br />
in which it appears. The estimate of the Coal Resource set out in Table 2 presented in this annual report are considered<br />
to be a true reflection of the UHG Coal Resource as at 30 November 2015, and have been carried out in accordance with<br />
the principles and guidelines of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore<br />
Reserves. The JORC Code (2012).<br />
Mr. Gary Ballantine is employed by the Group as Executive General Manager for Exploration and Geology. Mr. Ballantine<br />
is a member of the Australasian Institute of Mining and Metallurgy (Member #109105) and has over 25 years of experience<br />
relevant to the style and type of coal deposit under consideration and to the activity which is being undertaken to qualify<br />
as a Competent Person as defined by the Australasian Code for Reporting of Exploration Results, Mineral Resources and<br />
Ore Reserves, The JORC Code (2012).<br />
Due to rounding, discrepancy may exist between sub-totals and totals. Rounding rules refer to Clause 25 of the JORC<br />
Code (2012).<br />
In 2015, 16 boreholes were drilled within the UHG mining license, comprising 636m of HQ-3 drilling and 368m of<br />
122mm diameter open hole drilling, outside of the northern pit limit. The purpose of this drilling was to improve<br />
the geotechnical knowledge related to the boundaries of basement rock on the northern periphery of the UHG<br />
deposit. The information obtained allowed the revision to be made to the life-of-mine (“LOM”) pit slope design,<br />
subsequently allowing the revision of ex-pit dump design and the facilitation of shorter overburden haulage<br />
distances than previously determined during LOM planning. Data obtained from this drilling was not included<br />
in the JORC Coal Resource updated as of 30 November 2015, and is unlikely to have any bearing upon future<br />
updates.<br />
Annual Report 2015<br />
23