2011 Algae Platform Review – <strong>Reviewer</strong> <strong>Comments</strong><br />

<strong>Reviewer</strong> <strong>Comments</strong> are direct transcripts of commentary and material provided by the Platform’s<br />

Review Panel. They have not been edited or altered by the Biomass Program.<br />

<strong>Reviewer</strong> <strong>Comments</strong><br />

<strong>Reviewer</strong>: 1 Criteria Score: 5<br />

The device has been obtained as in shakedown studies. The real work begins now.<br />

<strong>Reviewer</strong>: 2 Criteria Score: 3<br />

The project ends in May 2011 and was considered 65% complete at the report interval. The lack of<br />

presentation of an energy budget at this stage of this energy conversion project is somewhat concerning.<br />

<strong>Reviewer</strong>: 3 Criteria Score: 8<br />

ODU has successfully selected, designed, and constructed a pilot-scale “algaenator” built around the<br />

design of a horizontal wiped-film reactor. It is recognized that significant progress has been achieved<br />

prior to funding by this program.<br />

<strong>Reviewer</strong>: 4 Criteria Score: 7<br />

Tested "algenator" which didn't work or this was determined from a desk study--not clear. Switched<br />

reactors and site.<br />

<strong>Reviewer</strong>: 5 Criteria Score: 5<br />

The project has made progress in achieving its intermediate goals but major components of the project<br />

(testing, optimization, and evaluation of conversion unit and characterization of products) are not<br />

complete. Unfortunately, it is likely that investigators will rush to "complete" this work by the project<br />

deadline (May 2011).<br />

<strong>Reviewer</strong>: 6 Criteria Score: 5<br />

The pilot plant demonstration facility is quite good. No results past that were really given other than PID<br />

diagrams and statements of hope. At minimum a thermodynamic analysis could be been calculated and<br />

presented.<br />

<strong>Reviewer</strong>: 7 Criteria Score: 5<br />

Detailed pilot data is avaiable, but were not presented.<br />

Presenter Response<br />

3. Project Relevance<br />

The project both identifies with and contributes to meeting the platform goals and objectives of the<br />

Biomass Program Multi-Year Program Plan<br />

The project has considered applications of the expected outputs<br />

<strong>Reviewer</strong> <strong>Comments</strong><br />

<strong>Reviewer</strong>: 1 Criteria Score: 5<br />

This may or may not turn out to be relevant. DOE should be pushing for a true determination of the value<br />

or potential for this technology by project end.<br />

<strong>Reviewer</strong>: 2 Criteria Score: 4<br />

Energy conversion processes are important, but must be demonstrated to be efficient to be a contributor to<br />

platform goals.<br />