Planning Authority Reports<br />
<strong>21</strong>. Footpaths are to be constructed in accordance with <strong>Council</strong>’s standard<br />
drawing SD1006 and located on one side of the internal road network.<br />
22. A court bowl radius of 8.5 m is to be provided at the termination of the<br />
subdivisional road to facilitate the turn movements of vehicles<br />
including service vehicles such as garbage trucks. The standard of<br />
construction shall be equal to a road being constructed.<br />
23. The provision of a reticulated water supply to the development with<br />
individual lot connections and fire plugs in accordance with <strong>Council</strong>’s<br />
specifications (min. pipe size 100mm) and the requirements of the<br />
Tasmanian Fire Service. The developer is to supply and install water<br />
meters to all allotments. Water meter type is to be approved by the<br />
Director Engineering Services.<br />
24. Water meters are to be located so as to afford unobstructed access to<br />
service personnel.<br />
25. The provision of a reticulated sewerage system to the development with<br />
individual lot connections and method of disposal in accordance with<br />
the requirements of the Director Engineering Services. The system is<br />
to be designed by a Chartered Professional Engineer.<br />
26. Street lighting is to be provided in accordance with the requirements of<br />
Aurora Energy Pty Ltd and the Director Engineering Services. The<br />
street lighting is to be designed to minimise off site glare and reflected<br />
light. The use of non-standard lighting poles is not permitted within<br />
the development.<br />
27. Underground power is to be provided to the development in<br />
accordance with the requirements of Aurora Energy Pty. Ltd. and<br />
<strong>Council</strong>’s standard drawings and specifications.<br />
28. Telecommunications infrastructure is to be provided to the<br />
development in accordance with the requirements of Telstra and<br />
<strong>Council</strong>’s standard drawings and specifications.<br />
29. A plan of management is to be prepared and submitted for the<br />
approval of the Director Engineering Services, prior to disturbance or<br />
construction, outlining information and proposed construction<br />
practices in relation to:<br />
<strong>Waratah</strong>-<strong>Wynyard</strong> <strong>Council</strong> – Ordinary Meeting <strong>Minutes</strong> – <strong>21</strong> <strong>January</strong> <strong>2008</strong> Page 37