Completed Projects from the 2011/14 MTIP<br />
Appendix 5 ‐ Completed, Delayed, and Deleted Projects<br />
County Lead Agency Project ID Title Description Completion Year Total Cost<br />
PLA<br />
PLA<br />
PLA<br />
PLA<br />
City of Rocklin Division of<br />
Engineering PLA25357 Safe School Route Phase 5<br />
City of Rocklin Division of<br />
Stanford Ranch Rd. Pavement<br />
Engineering<br />
PLA25503 Rehabilitation<br />
In downtown Rocklin: Construct new sidewalks and bicycle lanes on<br />
remaining unimproved existing streets, allowing access to<br />
Springview School, downtown, and adjacent residential<br />
neighborhoods. (Emission Benefits in kg/day: ROG 0.26, NOx 0.15,<br />
PM10 0.03) 2011 $2,897,856<br />
Reconstruct Stanford Ranch Rd. from Sunset Blvd. to Roseville City<br />
Limits. 2012 $2,014,844<br />
In Roseville, add micropave resurfacing to sections of Church St.,<br />
City of Roseville Dept of<br />
Public Works PLA25443<br />
Baseline Rd., Junction Blvd., Foothills Blvd., Atlantic St. & Pleasant<br />
2010 Arterial Micropave Project Grove Blvd. 2011 $1,337,225<br />
City of Roseville Dept of<br />
Public Works<br />
PLA25406<br />
Baseline Rd & Foothills Blvd<br />
CMS Installation Project<br />
In Roseville, install Changeable Message Signs (CMS) on S/B Foothills<br />
Blvd. south of Vineyard Road and E/B Baseline Road east of<br />
Fiddyment Road to reduce traffic congestion by improving traffic<br />
information dissemination per the ITS Master Plan. (Qualitative<br />
Emission Benefit Analysis on file.) 2012 $300,000<br />
PLA<br />
PLA<br />
City of Roseville Dept of<br />
Public Works PLA25375 Blue Oaks Extension<br />
City of Roseville Dept of<br />
Public Works PLA25415 Bus Purchase<br />
Roseville, Blue Oaks from 1300' west of Fiddyment to Hayden Pkwy.,<br />
extend as 2 lanes, including a 3 lane bridge over Kaseberg Creek. 2012 $3,200,000<br />
Replace three (3) DAR style buses with 3 low floor buses @ $130,000<br />
each. (FTA funds apportioned in FFY 2009.) 2012 $390,000<br />
PLA<br />
PLA<br />
PLA<br />
PLA<br />
PLA<br />
PLA<br />
City of Roseville Dept of<br />
Public Works PLA25361 Call Center<br />
One‐stop Call Center for all of South Placer County for human<br />
service/demand responsive transit. FFY 2006 5317 funds used. 2012 $250,000<br />
Roseville, Harding Blvd @ Dry Creek, I‐80 to Royer Park: Construct<br />
class 1 bikeway in 2 phases. Phase 1 from I‐80 to Harding Blvd<br />
completed in 2004 (PLA20870) completed in 2004. Phase 2<br />
construction is separated into 3 segments: Segment 2 is located<br />
City of Roseville Dept of<br />
I‐80 To Royer Park Bikeway from East Street to Folsom Road. (Emission benefits in kg/day: 0.25<br />
Public Works<br />
PLA25385 Phase 2 ‐ Segment 2<br />
ROG, 0.2 NOx 0.09 PM10) 2012 $413,592<br />
In Roseville, apply 2‐inch gap graded rubberized Asphalt to Industrial<br />
City of Roseville Dept of<br />
Industrial Ave. Rubberized Ave. from Washington Blvd. to Justice Center Dr. (Toll Credits for<br />
Public Works<br />
PLA25429 Overlay<br />
CON) 2012 $2,491,590<br />
City of Roseville Dept of<br />
Pleasant Grove Blvd: Extend 4 lanes from Fiddyment Rd to 1500 feet<br />
Public Works PLA25379 Pleasant Grove Blvd<br />
west of Market Street. 2007 $4,400,000<br />
City of Roseville Dept of<br />
Public Works PLA25404 Repower/Rehab Buses Repower/Rehab buses 2012 $1,215,000<br />
In Roseville, install fiber optic Conduit, cable & pull‐boxes along<br />
Cirby Wy, Rocky Ridge Dr, Old Auburn Rd, S Cirby wy, Rsvl Pkwy,<br />
Blue Oaks Blvd, Fiddyment Rd, Baseline Rd, Woodcreek Oaks Blvd,<br />
City of Roseville Dept of<br />
Junction Blvd & Foothills Blvd. Emission reduction benefits (kg/day):<br />
Public Works PLA25288 Roseville Fiber Optics Project ROG 0.32, NOx 0.32 2012 $964,319<br />
<strong>2013</strong> MTIP - Page 331 of 390<br />
Completed Projects: Page 4 of 27