Appendix 5 ‐ Completed, Delayed, and Deleted Projects<br />

Delayed Projects from the 2011/14 MTIP<br />

County Lead Agency Project ID Title Description Completion Year Total Cost<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong><br />

ELD192<strong>16</strong><br />

Country Club Dr ‐ Silva Valley<br />

Pkwy to ''Old Lincoln Hwy''<br />

Construct new 2‐lane road north of existing Tong Rd from Silva<br />

Valley Pkwy to the "Old Lincoln Hwy". This project is the first half of<br />

the ultimate project to connect Silva Valley Pkwy to Bass Lake Rd<br />

and provide parallel capacity to US50. (CIP71335) 2028 $6,285,200<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong><br />

ELD15990<br />

Diamond Springs Pkwy ‐ Phase<br />

1B<br />

Construct new 2‐lane divided arterial roadway from Missouri Flat Rd<br />

east of Golden Center Dr to a new T‐intersection with SR‐49 south of<br />

Bradley Dr; includes planning, environmental clearance, grading and<br />

right of way for the ultimate 4‐lane road, required improvements to<br />

SR‐49 and three new signals. See ELD19348/CIP72375 for Phase 1A<br />

and ELD19203/CIP72368 for Phase 2. (CIP72334) 2026 $24,085,800<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong><br />

ELD19232<br />

Latrobe Rd/White Rock Rd<br />

Connector (New Road)<br />

New connector road from the El Dorado Hills Business Park to White<br />

Rock Rd west of Four Seasons/Stonebriar intersection; Phase 1 to<br />

perform route alignment study and prepare PSR; Phase 2 will include<br />

environmental, design and construction; may require coordination<br />

with Sacramento County, City of Folsom, Southeast Connector JPA<br />

and area developers. (CIP661<strong>16</strong>) 2028 $19,391,100<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong> ELD<strong>16</strong>010 Saratoga Wy Ext ‐ Phase 1<br />

Construct new 2‐lane arterial to extend Saratoga Wy from current<br />

terminus near Finders Wy to Sacramento County Line; includes<br />

median, 6‐ft shoulders, right‐turn pocket onto Finders Way, asphalt<br />

path, drainage system, environmental clearance and secure ROW for<br />

future 4‐lane road from County Line to El Dorado Hills Blvd. (Phase 2<br />

CIP#GP147‐See ELD19234 in MTP.) CIP71324 2028 $11,541,350<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong><br />

ELD19177<br />

US 50/Cameron Park Dr<br />

Interchange <strong>Improvement</strong>s<br />

Interchange <strong>Improvement</strong>s: this project includes detailed study to<br />

identify capacity improvements alternatives and selection of<br />

preferred alternative; assumes reconstruction of existing US50<br />

bridges to widen Cameron Park Dr to 8 lanes under the overcrossing;<br />

road and ramp widenings. (CIP72361) 2028 $47,625,800<br />

ELD<br />

El Dorado County Dept of<br />

<strong>Transportation</strong><br />

ELD19173<br />

US 50/El Dorado Hills Blvd<br />

Pedestrian Overcrossing<br />

Construct ped/bike overcrossing over US 50 just east of El Dorado<br />

Hills Blvd Interchange; includes a Class 3 mixed‐use path;<br />

Construction and ROW acquisition for 10‐ft wide sidewalk and<br />

adjacent retaining walls, barriers, railings and landscape<br />

replacement included with CIP71323/ELD15630. (CIP71340) 2028 $6,783,000<br />

<strong>2013</strong> MTIP - Page 350 of 390<br />