Completed Projects from the 2011/14 MTIP<br />
Appendix 5 ‐ Completed, Delayed, and Deleted Projects<br />
County Lead Agency Project ID Title Description Completion Year Total Cost<br />
YOL<br />
Yolo County Dept of<br />
Public Works<br />
YOL19282<br />
Yolo County Smart Growth<br />
Implementation Project<br />
In Yolo County, develop a plan to measure, control, and reduce net<br />
greenhouse gas emissions and address economic and social<br />
adaptations of the county to the effects of climate change. 2011 $150,000<br />
YOL<br />
YOL<br />
YOL<br />
YOL<br />
Yolo County<br />
<strong>Transportation</strong> District YCT18248<br />
Madison Bus Stop<br />
<strong>Improvement</strong><br />
This project will design and construct a relocated bus stop serving<br />
the town of Madison. The bus stop will include a bus shelter, bench,<br />
garbage can, schedule display and solar lighting. 2012 $225,000<br />
Yolo County<br />
Transit system signage enhancement, including downtown<br />
<strong>Transportation</strong> District YCT18102 Signage Enhancement Sacramento for all agencies ‐ 2012 $62,500<br />
Yolo County<br />
YCTD FY 10 Preventive<br />
<strong>Transportation</strong> District YCT18099 Maintenance YCTD FY 10 Preventive Maintenance of Yolobus Transit Fleet 2011 $1,269,459<br />
Yolo County<br />
<strong>Transportation</strong> District<br />
YCT18<strong>16</strong>0<br />
Yolobus 13 Bus Purchase Cost<br />
Increase<br />
Increase in procurement cost of 13 ‐ 40’ ft fully equipped high‐floor<br />
transit buses. Due to changes in supply for the desired bus<br />
configuration and required power plant the new estimated cost of<br />
this procurement is approximately $460,000 per unit, $42,000 above<br />
previous estimates. 2011 $538,000<br />
YOL<br />
Yolo County<br />
<strong>Transportation</strong> District<br />
YCT18<strong>16</strong>7<br />
Yolobus Bus Stop Enhancement<br />
Project<br />
Enhance passenger safety, security, comfort, and information by<br />
installing (either adding or replacing) passenger shelters, benches,<br />
shelter and bench pads, solar lighting, information displays at<br />
several locations along Yolobus transit routes. 2011 $264,000<br />
YOL<br />
Yolo County<br />
<strong>Transportation</strong> District<br />
YCT18<strong>16</strong>6<br />
Yolobus ITS Projects/Universal<br />
Fare Card Project<br />
Retrofit and add to the transit fleet and transit operations various<br />
intelligent transportation system (ITS) products to enhance transit<br />
operation, passenger safety, passenger information, passenger trip<br />
planning, passenger mode choice, emergency response, system<br />
security and simplification of fare payment through the regions<br />
universal fare card fare collection system. 2012 $436,000<br />
YOL<br />
Yolo County<br />
<strong>Transportation</strong> District<br />
YCT18<strong>16</strong>2<br />
Yolobus Rehabilitation and Repower<br />
of Nine (9) Transit Buses<br />
YUB Caltrans District 3 CAL20390 SR 65 Maintenance<br />
YUB Caltrans District 3 CAL20445 Yub‐20 Pavement Rehab<br />
YUB Caltrans District 3 CAL18835 Yub‐70 E Street Bridge Rehab<br />
Rehabilitation and re‐power of nine (9) buses to extend their useful<br />
life 2011 $1,350,000<br />
From 3 mi north of Wheatland to 0.9 mi south of Jct SR 70: Perform<br />
highway maintenance. 2011 $3,803,000<br />
Near Marysville, from 0.1 mile east of Levee Road to 0.1 mile west of<br />
Loma Rica Road ‐ Pavement rehabilitation (PM R3.5/8.0) [CTIPS ID<br />
107‐0000‐0848]. 2012 $4,791,000<br />
Yuba County, in Marysville, at Yuba River Bridge Overhead #<strong>16</strong>‐34 ‐<br />
Rehabilitate bridge deck (PM 15.4/25.8) 2011 $3,850,900<br />