12.01.2015 Views

Module 5 - VicForests

Module 5 - VicForests

Module 5 - VicForests

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

4 3BAudit Findings<br />

Table 4-20<br />

Summary of compliance findings for the Road construction Compliance Element<br />

Compliance<br />

Element<br />

Road construction<br />

Total compliance 71<br />

Total noncompliance<br />

6<br />

Non-compliance EIA breakdown<br />

Severe 0<br />

Major 0<br />

Moderate 4<br />

Minor 0<br />

Negligible 2<br />

No impact 0<br />

A non-compliance was identified in relation to an apparent uncontrolled disposal of fill (C3). It was<br />

observed during the audit that a significant quantity (estimated at approximately five cubic metres) of<br />

soil, apparently resulting from the construction of the coupe driveway, had been pushed up around a<br />

number of live trees adjacent to the road within a mapped rainforest and streamside buffer and had<br />

not been stabilised through revegetation or other means. Erosion of the stockpiles by rainfall was<br />

evident at the time of the audit. No records showing that this fill disposal site had been planned were<br />

available (Refer to Appendix K, Photograph 10).<br />

A senior DSE officer advised the Auditor that <strong>VicForests</strong>, at the time of road construction, had<br />

discussed options to minimise disturbance to the several wet gullies that the road crosses. According<br />

to DSE, it was agreed that the soil should be stockpiled to enable to road to be rehabilitated (including<br />

ripping and spreading of topsoil) after completion of harvesting of an adjacent coupe, which also used<br />

the road. The DSE officer also advised that the stockpiling of the soil against the trees was agreed as<br />

the option of lesser environmental impact compared with increasing the clearing width. The Auditor<br />

acknowledges the apparent consideration that was given to various options to minimise environmental<br />

impact and that <strong>VicForests</strong> plans to rehabilitate the road to a higher level than the minimum required.<br />

In light of this information, the Auditor considers that the main deficiency appears to be in documenting<br />

plans and obtaining approvals for this work, given that the activities have resulted in outcomes not<br />

aligned with the Code and Management Procedures (soil stockpiles not appropriately stabilised and<br />

soil stockpiled against live trees). The EIA risk rating for this non-compliance was determined as<br />

Moderate. The Auditor recommends that, once complete, the rehabilitation of this road, including<br />

timeliness of rehabilitation, is reviewed by DSE as the regulator against what was said to have been<br />

agreed.<br />

Failure to plan for and stabilise excess fill also resulted in non-compliance on two other coupes (C8<br />

and C13), however, the EIA risk ratings were determined as Negligible due to the small quantity of fill<br />

involved and its location away from environmentally sensitive or excluded areas.<br />

Three non-compliances with Moderate EIA risk ratings were identified where fill slopes of roads<br />

traversing slopes were not adequately consolidated (C20, C22 and C24). A tension crack was<br />

observed in the road surface at one coupe (C20), suggesting potential instability of the road (Refer to<br />

Appendix K, Photograph 11) and erosion of fill slopes was evident (Refer to Appendix K, Photographs<br />

7 and 8).<br />

42 42807504/01/01

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!