02.03.2015 Views

COPY OF FINAL PROSPECTUS - Mirabela Nickel

COPY OF FINAL PROSPECTUS - Mirabela Nickel

COPY OF FINAL PROSPECTUS - Mirabela Nickel

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

• a throughput of four million tonnes per annum has been determined to be<br />

optimal for the proposed mill;<br />

• tests indicate that from a nickel feed grade of approximately 0.62%, a nickel<br />

concentrate grade of 13.5% can be achieved using a conventional flotation<br />

processing system, at a recovery of between 66% and 68%;<br />

• assuming a throughput of four million tonnes per annum, a nickel feed grade<br />

of 0.62% and a recovery of 67%, management believes that the Santa Rita<br />

Project will be capable of producing an average of approximately 16,000 tonnes<br />

of nickel in concentrate per annum using a conventional flotation processing<br />

system;<br />

• a pit optimization study estimates the following resource and strip ratio within<br />

open pit limits:<br />

Strip Ratio<br />

t waste/t potential<br />

Classification Mt Ni (%) mill feed<br />

Indicated .............................. 49.5 0.61 5.9<br />

Inferred ............................... 6.2 0.55 5.9<br />

• assuming a throughput of four million tonnes per annum, the pit optimization<br />

study also estimates that the Santa Rita resource has the potential for a mine<br />

life in excess of ten years;<br />

• capital costs (including processing plant, infrastructure, port facilities,<br />

environmental commissioning, first fills and spare parts), estimated to an<br />

accuracy of 30% and after providing for a 10% contingency, are expected to<br />

be approximately US$223 million;<br />

• processing costs are estimated to be US$6.77 per tonne of ore and mining costs<br />

(including a capital expenditure of US$64 million on mining fleet) are<br />

estimated to be approximately US$1.10 per tonne of material mined;<br />

• <strong>Mirabela</strong> has concluded agreements to purchase a total of approximately<br />

1,756 hectares comprising all of the land that management believes will be<br />

required for the Santa Rita Project;<br />

• <strong>Mirabela</strong> has been issued a Licença de Localização, a preliminary<br />

environmental licence, representing approval of the Santa Rita Project by the<br />

local communities and conditional approval by the State Environmental Board<br />

of Bahia, Brazil; and<br />

• subject to a positive outcome of the BFS, management believes that it is on<br />

schedule to obtain all requisite permits and approvals to commence<br />

construction by late 2007, and commence production in early 2009.<br />

The pit optimization study referred to above from which the economic analysis of<br />

the Santa Rita Project was derived is preliminary in nature and includes inferred<br />

mineral resources that are considered too speculative geologically to have the<br />

economic considerations applied to them that would enable them to be categorized<br />

as mineral reserves, and there is no certainty that the results described in the<br />

study will be realized.<br />

Mineral resources that are not mineral reserves do not have demonstrated<br />

economic viability.<br />

2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!