ACTIVITY 6: REHABILITATION OF FEEDER ROADS<br />
Activity Objective:<br />
To reduce transportation costs and time by rehabilitating up to 950 km of Feeder Roads in eight (8)<br />
Districts in the Intervention Zones in order to:<br />
i. Increase access to major domestic and international markets.<br />
ii. Facilitate transportation linkages from rural areas to social service networks (including, for<br />
instance, hospitals, clinics and schools).<br />
QTR 11 PROGRESS<br />
1.6 FEEDER ROADS<br />
INDICATOR: Value of Signed Contracts for Feeder Road Works (USD 62,436,571)<br />
TARGET(ANNUAL) APR ACTUALS FOR THE QUARTER CUMMULATIVE TO DATE<br />
2009- MAR 2010<br />
(OCT - DEC 2009)<br />
USD 24,436,011 USD 18,443,422.17 USD 18,443,422.17<br />
INDICATOR: Kilometers of Feeder Roads completed (406km)<br />
TARGET(ANNUAL) APR ACTUALS FOR THE QUARTER CUMMULATIVE TO DATE<br />
2009- MAR 2010<br />
(OCT - DEC 2009)<br />
N/A 1 N/A N/A<br />
ACTIVITY STATUS NEXT STEPS<br />
LOT 1(NR series)<br />
i. Close/Open Bids for NR<br />
Series.<br />
ii. Commence Evaluation of<br />
Bids for NR Series.<br />
iii. Obtain MCC Approval for<br />
BEP Report on NR Series<br />
iv. Obtain <strong>MiDA</strong> Board<br />
Approval of Recommended<br />
Contractors for NR Series.<br />
LOT 2 (EC series)<br />
Obtain Performance<br />
Securities.<br />
• Bids were submitted and opened on<br />
28 th October, 2009.<br />
• Evaluation of Bids started on 9 th<br />
November, and was completed on<br />
23 rd November, 2009.<br />
• MCC and Board approvals for<br />
Award of Contracts to Respective<br />
Contractors were obtained on 9 th<br />
December, 2009.<br />
• Letters of Acceptance were issued<br />
to Respective Contractors on 10 th<br />
December, 2009.<br />
• Performance Guarantees were<br />
submitted to <strong>MiDA</strong> on 31 st<br />
December, 2009.<br />
• Performance Securities for Lots<br />
EC2 & EC3 were received on 2 nd<br />
October, 2009<br />
• Performance Security for EC1 was<br />
received on 12 th October, 2009.<br />
• Sign Contract with<br />
Respective Contractors.<br />
• Mobilize to commence the<br />
works.<br />
1 Targets have been earmarked for <strong>report</strong>ing in Year 4.<br />