N.1 LOT 2 (TQM) Activity Timelines<br />
Output/Process<br />
Handing Over of Site<br />
Section 2, CH. 8+600 - 12+500<br />
Section 3, CH. 6+000 - 7+500<br />
Section 4, CH. 7+500 - 8+600<br />
Section 5, Interchange Loop<br />
Pre-Commencement A ctivities<br />
Establishment of Contractor’s<br />
& Engineers Offices<br />
Set up Contractor’s Laboratory,<br />
Plant & Equipment<br />
Kick Off meeting<br />
Earthworks<br />
General Works<br />
Filling<br />
Pavement works<br />
Sub-Base and Base material<br />
Drainage Works<br />
Insitu Concrete works<br />
Pipeworks<br />
18 th – 28 th FEBRAURY, 2010<br />
DECEMBER 2009 – MARCH 2010<br />
DECEMBER, 2009 – MARCH , 2010<br />
JANUARY 2010 – OCTOBER 2011<br />
DECEMBER 2009 – MARCH 2010<br />
FEBRUARY 2010 – MARCH 2010<br />
DECMBER 2009 – FEBRUARY 2010<br />
2010<br />
JAN FEB MAR APR MAY JUN<br />
JANUARY 2010 – MARCH 2010<br />
30 th MARCH, 2010<br />
30 th MARCH, 2010<br />
31 st MARCH , 2010<br />
DECMBER 2009 – FEBRUARY 2010<br />
30 th APRIL, 2010<br />