ACTIVITY 3: FINANCIAL SERVICES<br />
<strong>Ghana</strong> Rural Bank Computerization and Interconnectivity Project (GRBCIP)<br />
The <strong>full</strong> complement of Consultants, Contractors and Suppliers are all now in place and making progress<br />
with respect to Project timelines.<br />
There were a number of impediments and challenges which were as follows: (i) the complexity of the<br />
Project created inter-dependency challenges, (ii) delays in making advance Payments to the Contractors<br />
supplying Equipment, thus delaying ordering of equipment, (iii) the unsuitability of the proposed Disaster<br />
Recovery Site which necessitated a change of the Site, and (iii) delay in the arrival of the Central Server<br />
for installation.<br />
Strategies adopted to mitigate the challenges include (i) developing a rigorous integrated Implementation<br />
Plan which took care of the various Contractor/Supplier performance and deployment inter-dependencies,<br />
(ii) deploying additional Resources to expedite the Confirmation of Advance Payment Guarantees as<br />
required of Consultants/Contractors in the Procurement process, (ii) liaised with Apex Bank and GhIPSS<br />
for the allocation of an alternative Site at GhIPSS to host the Disaster Recovery Site, and (iv) arranging a<br />
temporary Server which was used as a Central Server prior to the arrival of the main supplies of<br />
Equipment.<br />
With the above challenges and impediments resolved, the Timelines for the Project is on track and<br />
expected to be completed on schedule.<br />