Output/Process<br />
Community Services: Water & Sanitation<br />
OCT’09 NOV’09 DEC’09 JAN’10 FEB’10 MAR’10<br />
South Zone – 86 Boreholes and 9 Pipe<br />
Extensions identified and diligenced (10-<br />
09-09) Detailed designs for next quarter.<br />
Northern Zone – Contract signed (19-06-<br />
09); 58 Boreholes and 1 Small Town Water<br />
Supply System. Inception and Draft<br />
Feasibility Reports submitted. Detailed<br />
designs submitted and finalised.<br />
Feasibility of Tamale Water Extension<br />
Project (Contract Signed: 11-09-09)<br />
Inception <strong>report</strong> submitted. Feasibility<br />
studies submitted. Detailed design<br />
submitted.<br />
Afram Basin – Contract signed (13-08-<br />
09); Feasibility of 93 Boreholes and 13<br />
Small Town Water Systems in progress.<br />
Inception submitted. Feasibility submitted.<br />
Procurement of IDIQ contractors (July-<br />
Nov, 09). Evaluation <strong>report</strong> under review.<br />