Output/Process<br />

Community Services: Water & Sanitation<br />

OCT’09 NOV’09 DEC’09 JAN’10 FEB’10 MAR’10<br />

South Zone – 86 Boreholes and 9 Pipe<br />

Extensions identified and diligenced (10-<br />

09-09) Detailed designs for next quarter.<br />

Northern Zone – Contract signed (19-06-<br />

09); 58 Boreholes and 1 Small Town Water<br />

Supply System. Inception and Draft<br />

Feasibility Reports submitted. Detailed<br />

designs submitted and finalised.<br />

Feasibility of Tamale Water Extension<br />

Project (Contract Signed: 11-09-09)<br />

Inception <strong>report</strong> submitted. Feasibility<br />

studies submitted. Detailed design<br />

submitted.<br />

Afram Basin – Contract signed (13-08-<br />

09); Feasibility of 93 Boreholes and 13<br />

Small Town Water Systems in progress.<br />

Inception submitted. Feasibility submitted.<br />

Procurement of IDIQ contractors (July-<br />

Nov, 09). Evaluation <strong>report</strong> under review.<br />

- 96 -