PROJECT 2: TRANSPORTATION PROJECT<br />
Objective:<br />
To reduce Transportation cost affecting Agricultural Commerce at the Sub-Regional and Regional levels,<br />
in order to improve the Competitiveness of Agricultural Producers using Roads in the Intervention Zones.<br />
QTR. 11 PROGRESS<br />
2.1 N1 ACTIVITY<br />
INDICATOR: Percent of Contracted Road Works disbursed: N1 Lot 1 (100%)<br />
TARGET(ANNUAL) ACTUALS FOR THE QUARTER CUMMULATIVE TO DATE<br />
APR 2009- MAR 2010<br />
(OCT-DEC 2009)<br />
41.6% 5.35% 17.80%<br />
ACTIVITY STATUS NEXT STEPS<br />
i. Carry out General<br />
Excavation and Filling<br />
Works on Ch. 2+000<br />
to Ch. 4+900<br />
• Actual Physical Completion achieved<br />
was 19.64% as against Planned Physical<br />
Completion of 22.7 %.<br />
• Supervision Reports on Monthly<br />
Progress of N1 Lot 1 Main Works<br />
obtained.<br />
• Monthly Technical Meetings for N1 Lot<br />
1 Construction Works organized.<br />
- 27 -<br />
• Clear Site of structures.<br />
• Carry out Earthworks<br />
• Execute Drainage Works<br />
• Continue Foundation for<br />
Bridge and Retaining Walls<br />
at Dimples Interchange<br />
INDICATOR: Percent of Contracted Road Works disbursed: N1 Lot 2 (100%)<br />
TARGET(ANNUAL)<br />
APR 2009- MAR 2010<br />
ACTUALS FOR THE QUARTER (OCT-<br />
DEC 2009)<br />
CUMMULATIVE TO<br />
DATE<br />
41.6% 10% 10%<br />
ACTIVITY STATUS NEXT STEPS<br />
i. Sign Contract with<br />
Messrs.MSF.<br />
• <strong>MiDA</strong> signed Contract with Messrs.<br />
Moniz da Maia Serra & Fortunato-<br />
Empereiteros (MSF), the Contractor for<br />
ii.<br />
iii.<br />
Issue Notice to<br />
Commence N1 Lot<br />
2 Works.<br />
Carry out pre-<br />
Construction<br />
Activities<br />
N1 Lot 2 on 1 st October, 2009.<br />
• ICT-BANS JV issued Notice of Works<br />
commencement on 14 th October, 2009<br />
• 23 rd December, 2009.<br />
• <strong>MiDA</strong> handed over Section 1(Km<br />
12+500 to Km 14+119) to Contractor<br />
on 15 th October, 2009.<br />
• Contractor submitted of evidence of<br />
insurance on 13 th November, 2009.<br />
• <strong>MiDA</strong> received Contractor’s revised<br />
Work Program and Method Statement<br />
on 15 th December, 2009.<br />
• Environmental Baseline Survey <strong>report</strong>,<br />
revised EMP, revised Health and<br />
Safety Management Plans were<br />
received on 15 th December, 2009.<br />
• ICT BANs and Messrs. MSF jointly<br />
inspected Utility Relocation Works at<br />
• Hand over all Sections of<br />
N1 Lot 2.<br />
• Complete topographic<br />
surveys for entire<br />
corridor.<br />
• Complete Pile foundation<br />
tests on Site.<br />
• Commence STI and AID<br />
awareness on site<br />
• Complete investigations<br />
on Quarries and Borrow<br />
pits.