Transportation and Agriculture Infrastructure Projects<br />
Key Project Data<br />
Consultancy: Irrigation Development (LOT 2)<br />
Rehabilitation/Extension Works on 4 Selected Irrigation Schemes in the<br />
Project Name Afram Basin Zone<br />
Client<br />
Consultant<br />
Type of Service<br />
Millennium Development Authority (<strong>MiDA</strong>), Accra, <strong>Ghana</strong><br />
Haskoning Nederland BV, ABP Consult Ltd. and SAL Consult Limited<br />
Consultancy Services for the Provision of Feasibility Study, Final Design<br />
and Construction Supervision of Rehabilitation/Extension Works on<br />
irrigation Schemes in the Afram Basin Zone<br />
Cost of Consultancy<br />
Assignment The Cost of Consultancy assignment is US$ 1,998,113.00<br />
Disbursement to Date<br />
Project Description<br />
Project Location<br />
Funding<br />
Contract Package N/A<br />
Contract Signed on<br />
Date 21 st October, 2009<br />
Commencement Date 11 th November, 2009<br />
Nil<br />
Phase A<br />
• Conduct Feasibility Study, Preliminary Designs<br />
• Assessment of Environmental and Social Impacts<br />
• Preparation of EMPs, Resettlement Plans,<br />
• Organizational and Management Capacity Assessment in the<br />
Operation of the Rehabilitated Schemes.<br />
Phase B<br />
• Preparation of Final Engineering Designs<br />
• Bidding and Evaluation of Bids for the Construction Works<br />
Phase C<br />
• Supervision of Construction Works involved in the Rehabilitation,<br />
Extension and /or Construction of the Schemes.<br />
• Establishment of the Appropriate Operational and Management<br />
Systems on Rehabilitated Schemes.<br />
• Post Construction Supervision during Defects Liability Period.<br />
Northern Region<br />
Phase A – Inception Report, Environmental Scoping Report, draft Feasibility<br />
Study (Incl. Preliminary Design Report, Draft EIA and EMP),<br />
Organizational and Management Needs Assessment Report and Final<br />
Feasibility Report– MCC<br />
Date of Completion 31 st December, 2011<br />
Duration of Project Phase A – 4 months; Phase B – 5 months; Phase C – 30 months<br />
Time Elapsed till<br />
Date<br />
1.5 months<br />
- 78 -