ANNEX B:<br />

Transportation Project Technical Report<br />

Transportation and Agriculture Infrastructure Projects<br />

Key Project Data<br />

Consultancy: N1 Highway Project<br />

Project Name<br />

Client<br />

Consultant<br />

Upgrading of N1 Highway between Tetteh Quarshie Interchange and<br />

Mallam Road Junction, Accra, <strong>Ghana</strong> to 3 lane Dual Carriageways with<br />

Adequate Public Transport Facilities and Grade Separated Structures.<br />

Millennium Development Authority (<strong>MiDA</strong>), Accra, <strong>Ghana</strong><br />

Intercontinental Consultants & Technocrats Pvt. Ltd (ICT), New Delhi,<br />

India in Joint Venture with Bans Consult Ltd, Accra, <strong>Ghana</strong><br />

Type of Service<br />

Cost of Consultancy<br />

Assignment<br />

Disbursement to Date<br />

Total Project Lengths<br />

Other Project<br />

Requirements<br />

Project Location<br />

Funding<br />

Contract Packages<br />

Feasibility Studies, Detailed Engineering Design including Preparation<br />

of EIA, RAP, Tender Documents and Construction Supervision.<br />

The Cost of Consultancy assignment is US$ 1,767, 425 (Foreign<br />

component) and GH¢ 1,303,409 (Local component)<br />

US$810,805.95 and GHC880,308.75<br />

14.10 Kms<br />

Grade Separated Structures and other Public Transport Facilities<br />

Within the Capital City in the Greater Accra Region and forms an<br />

Integral Part of the ECOWAS Trans West African Coastal Highway<br />

Network<br />

Phase I – Improvement Works and Design Part of Phase II - MCC<br />

Two<br />

Contract Signed Date 28 th December, 2007<br />

Commencement Date 7 th January, 2008<br />

Date of Completion Phase II: Construction Supervision commenced January 2009.<br />

Duration of Project 2 years from the effective date of Contract<br />

Variation of Contract ICT-BANS JV re-negotiated a Variation in Contract<br />

Time Elapsed till date 24 Months<br />

- 68 -