Transportation and Agriculture Infrastructure Projects<br />

Key Project Data<br />

Consultancy: KIA_PCC Project<br />

Consultant Services for a Perishable Cargo Centre at Kotoka International<br />

Project Name Airport (KIA-PCC)<br />

Client<br />

Consultant<br />

Type of Service<br />

Millennium Development Authority (<strong>MiDA</strong>), Accra, <strong>Ghana</strong><br />

Vek Adviesgroep B.V. in Association with Adviesburo Verhoef B.V. and<br />

Architectural & Engineering Services Limited (AESL)<br />

Consultancy Services for a Perishable Cargo Centre and Design of new<br />

Palletization facility at KIA.<br />

Cost of Consultancy<br />

Assignment The cost of consultancy assignment is US$1,450,000.00 and GHC 36,000.00<br />

Disbursement to Date<br />

Project Description<br />

Project Location<br />

Funding<br />

Contract Package One<br />

Contract Signed on<br />

Date 2 nd June, 2009<br />

Commencement Date 16 th June, 2009<br />

Nil<br />

Phase A<br />

• Review of Designs, Bidding Documents, Bill of Quantities, Cost and<br />

Returns, Design Preparation of Bidding Document of a New<br />

Palletization facility at KIA<br />

• Prepare Environmental Review and Environmental Assessment<br />

Report<br />

Phase B<br />

• Bidding and Evaluation of Bids for the Construction Works<br />

• Supervision Services for the Construction and Installation of<br />

Equipment in the PCC<br />

Phase C<br />

• Post Construction and Installation Services during Defects Liability<br />

Period.<br />

Greater Accra Region of <strong>Ghana</strong><br />

Phase A – Inception Report, Economic Viability Statement, Environmental<br />

Review Report and Assessment Register, Final Design Report and Bidding<br />

Documents– MCC<br />

Date of Completion 28 th August 2008<br />

Duration of Project Phase A – 7.5 months; Phase B – 14 months; Phase C – 12 months<br />

Time Elapsed till Phase A 6.5 months<br />

Date<br />

- 76 -