Transportation and Agriculture Infrastructure Projects<br />
Key Project Data<br />
Consultancy: KIA_PCC Project<br />
Consultant Services for a Perishable Cargo Centre at Kotoka International<br />
Project Name Airport (KIA-PCC)<br />
Client<br />
Consultant<br />
Type of Service<br />
Millennium Development Authority (<strong>MiDA</strong>), Accra, <strong>Ghana</strong><br />
Vek Adviesgroep B.V. in Association with Adviesburo Verhoef B.V. and<br />
Architectural & Engineering Services Limited (AESL)<br />
Consultancy Services for a Perishable Cargo Centre and Design of new<br />
Palletization facility at KIA.<br />
Cost of Consultancy<br />
Assignment The cost of consultancy assignment is US$1,450,000.00 and GHC 36,000.00<br />
Disbursement to Date<br />
Project Description<br />
Project Location<br />
Funding<br />
Contract Package One<br />
Contract Signed on<br />
Date 2 nd June, 2009<br />
Commencement Date 16 th June, 2009<br />
Nil<br />
Phase A<br />
• Review of Designs, Bidding Documents, Bill of Quantities, Cost and<br />
Returns, Design Preparation of Bidding Document of a New<br />
Palletization facility at KIA<br />
• Prepare Environmental Review and Environmental Assessment<br />
Report<br />
Phase B<br />
• Bidding and Evaluation of Bids for the Construction Works<br />
• Supervision Services for the Construction and Installation of<br />
Equipment in the PCC<br />
Phase C<br />
• Post Construction and Installation Services during Defects Liability<br />
Period.<br />
Greater Accra Region of <strong>Ghana</strong><br />
Phase A – Inception Report, Economic Viability Statement, Environmental<br />
Review Report and Assessment Register, Final Design Report and Bidding<br />
Documents– MCC<br />
Date of Completion 28 th August 2008<br />
Duration of Project Phase A – 7.5 months; Phase B – 14 months; Phase C – 12 months<br />
Time Elapsed till Phase A 6.5 months<br />
Date<br />
- 76 -