Rural Electrification: Final Detailed Design Reports on the provision of a 26km, 33kV O/H<br />

Lines and 10 Transformer Stations in the SHB and 67km, 33kV O/H Lines and two (2)<br />

Transformer Stations in the NAZ have been completed and reviewed. Tender Documents<br />

have been completed and ready to be issued.<br />

Tamale Water Extension Project (TWEP): Feasibility Studies on the Tamale Water<br />

Extension Project have been completed and reviewed. Draft detailed Designs are ongoing.<br />

iii.<br />

Selection of Indefinite Delivery, Indefinite Quantities (IDIQ) Consultants<br />

Bid Evaluations have been completed for the selection of IDIQ Works Contractors for<br />

Education, Water and Sanitation Facilities.<br />

iv.<br />

Implementing Entity Agreements (IEAs)<br />

Ministry of Local Government and Rural Development: Four (4) Regional Workshops<br />

planned to take place in all the three (3) Intervention Zones, were rescheduled to start in<br />

February 2010. The Workshops are intended to sensitize the new District Authorities about<br />

their roles and responsibilities under the Compact.<br />

Financial Services Activity<br />

The Cheque Codeline Clearing System was stabilized in the Accra Tema Clearing Zone with<br />

over 80% of the country’s cheques handled by the System.<br />

Bid Document for the procurement of Consultant for the Legal Review of Payment System<br />

Laws was issued in October 2009 and the Technical Evaluation of the three Bids received<br />

was completed in December 2009.<br />

(4) OTHER ACTIVITIES<br />

(i) Program Audits<br />

Internal: The Internal Audit Team completed the audit of the Credit Activity. The audit<br />

focused on Disbursements to Participating Financial Institutions in the Northern, Volta,<br />

Eastern and Ashanti Regions. As part of the audit, the Team visited the Rural Banks, Farmer<br />

Based Organizations and farming outlets.<br />

The Audit Team also held meetings with Project Teams to understand the major risks<br />

associated with the various Projects. The information gathered will assist the Audit Team in<br />

the preparation of the 2010 Internal Audit Annual Plan.<br />

External: Messrs PricewaterhouseCoopers completed the Financial Audit of MCC Resources<br />

for the period ended June 2009. <strong>MiDA</strong> is awaiting Office of Inspector General’s approval of<br />

the External Audit Report.<br />

(ii) Zonal Advisory Committees<br />

The Second Round of District Advisory Committee (DAC) Meetings were held in 17<br />

Districts – 12 in the Southern Zone, and all the five (5) Districts in the Northern Zone. The<br />

Second Round Meetings built on the First Round Meetings held in all the Districts in the<br />