11.07.2015 Views

January 2012 Capital Investment - National Grid

January 2012 Capital Investment - National Grid

January 2012 Capital Investment - National Grid

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Exhibit ___ (EIOP-19)Page 47 of 684and crumbling foundations especially some of the tower supports. The containment pitaround the single phase transformers of TB#4 have collapsed in sections. The 115kVyard has inadequate thermal performance with respect to the existing transmissionsystem in the <strong>Capital</strong>/Northeast Region, which will be exacerbated by the addition ofGlobal Foundries (Luther Forest) and projected load growth. This will worsen with timeas Global Foundries is connected to the Northeast Region transmission system and asthe load grows as projected.Given the uncertainty over the 230kV station and the necessity to reduce capitalinvestment to minimize Plan costs, the Company has postponed both the 230kV and115kV rebuilds at Rotterdam. Any asset issues that arise will now be managed throughthe normal damage / failure process.Dunkirk (C05155) $0.25mDunkirk is a 230/115kV station located south of Buffalo, connected to 522MW ofgeneration owned by NRG. The Company retains ownership of most of the 230kV and115kV switch yard; however, the controls are located in the generation control roomowned by NRG. This station has recently experienced several 230kV misoperations dueto control cable issues as detailed in the 2010 Asset Condition report. Completereplacement of control cables is not possible due to space constraints in shared areas.In addition, portions of the station may require significant modification to conform toNPCC requirements.A project was completed in September 2010 to install a new cable trench in the 230kVyard. Control cables deemed “faulty” can then be replaced using these new facilities. Athorough conceptual engineering analysis to construct a new control house andcompletely separate assets in this station has been finished. Other equipment atDunkirk, such as disconnects and PTs (potential transformers), will be replaced during aseparate project to install a second bus tie.Lockport (C35464) $0mLockport is a 115kV transmission station with thirteen 115kV transmission lines tyingthrough the East and West bus sections. This station is critical to the 115kV systemoperations of Western New York. The overall condition of the station yard and controlroom is poor. As discussed in the 2011 Asset Condition report, work is required oncontrol cable duct banks, breaker operators, steel structures and concrete foundationsthat are deteriorated significantly. In addition, support column and breaker foundationsare in a deteriorated condition and need to be repaired with several potentially needingfull replacements. 18 The control room building is also in very poor condition withincreasing costs to maintain the original roof and the brickwork.There are two new 115kV SF6 breakers at Lockport, while the remaining 115kV oil filledBZ0 breakers show exterior corrosion and oil leaks. Three of the 115kV oil breakershave hydraulic mechanism leaks common to the BZO style breakers and failures ofhydraulic system components have been increasing. Each of the BZO breakers also has18 Report on the Condition of Physical Elements of Transmission and Distribution Systems, Case 06-M-0878 October 1, 2009, Page III-74 to III-76.II-3048

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!