Brennan Paving & Construction<br />
Hwy 407 East Extension - Durham Region (Construction General Partnership)<br />
Brennan Paving and Construction was awarded work on the Highway 407 East Extension project for pre-cast culverts and structures,<br />
sewer and grading works in August 2013. Ground breaking<br />
commenced promptly in September 2013. On-site management and<br />
field staff work diligently to ensure all activities are done at above<br />
normal standards from office related to on-site works. Our team at<br />
the 407 project is fully committed to ensuring that The Miller Group<br />
is recognized for quality, safety and efficiency of work. The COR program<br />
has already been implemented on this project, getting ready<br />
for certification.<br />
Our team strives to have an above standard working relationship<br />
<strong>with</strong> our Client and sub-contractors to ensure work proceeds in a<br />
Brennan Paving & Construction<br />
GTA Construction – Concrete Paving MTO 2010-2001 (Hwy 404 Extension)<br />
The project involved concrete paving for the 404 extension<br />
from Green Lane to Queensville Side Road.<br />
For this project, Miller Concrete supplied the concrete for the<br />
project <strong>with</strong> our Erie Strayer Portable Concrete batch plant.<br />
Mainline Pavement was placed <strong>with</strong> our Gomaco PS-2600<br />
Placer/Spreader, Gomaco GHP-2800 2-Lane Paver and Gomaco<br />
IDBI (In-the-pan dowel bar inserter). During placement,<br />
in order to provide a smooth riding surface, a Gomaco GSI<br />
Smoothness Indicator was utilized. Deceleration lanes were<br />
completed <strong>with</strong> our Gomaco Commander III and CMI MTP-<br />
4004 Belt Placer.<br />
Earth excavation on Hwy 407 East Extension<br />
Cast-in-place concrete in Con-Span pre-cast culvert footings<br />
This section of the Hwy 407 was originally awarded to another contractor but the Hwy 407 East<br />
Group had serious doubts of that contractor’s capability of fulfilling the high expectations of<br />
the Group. They subsequently awarded the project to Brennan Paving.<br />
This new section includes, among other activities, 500,000 m3 of earth excavation and supply<br />
and placement of over 400,000 tons of Granular A from Miller’s Carden Quarry. Day after day,<br />
the Hwy 407 East Group looks at Brennan and Miller as reliable and dependable resources to<br />
assure excellent quality of<br />
work and on-time delivery.<br />
smooth, efficient, and profitable manner. Since the start of<br />
the project, 407ECGP contract administrators have looked<br />
for Brennan’s assistance on items which are beyond the<br />
original contract. Brennan has attained additional work by<br />
not only having a great relationship <strong>with</strong> the Client, but also<br />
<strong>with</strong>in the team at the 407 project. That way, Brennan has<br />
become the “Contractor of Choice” by the 407ECGP Team.<br />
Brennan was recently awarded another section of earth<br />
work in the west area (Segment A1) of the new highway.<br />
The Hwy 407 East Group needed to accelerate construction<br />
operations and they knew that Brennan would achieve any<br />
commitments we made on the project.<br />
Different Divisions of<br />
the Miller Group; Miller<br />
Aggregates, Miller Concrete,<br />
Transportation and<br />
Logistics, Miller Paving, Installation of pre-cast culvert arches<br />
and Brennan, have come<br />
together on the Hwy 407 East project to show once again that<br />
we are Only the Best!<br />
The Spider Saw in action<br />
Miller Paving utilized our ‘spider saw’ on this project.<br />
Unique in Canada to The Miller Group, this equipment<br />
performs the transverse relief cutting for our concrete<br />
paving work. Not only does this equipment ensure<br />
a perfect linear cut across the joint; it is also capable<br />
of performing this work at approximately double the<br />
rate as per conventional methods – ensuring that no<br />
random cracks develop due to late sawcutting.<br />
Miller Paving received a bonus on the concrete paving for the project due to the high level of quality associated <strong>with</strong> the ready<br />
mix concrete that was supplied and for the smoothness of the end product. This high level of quality proves our position <strong>with</strong>in<br />
the industry as – ONLY THE BEST!<br />
METROLINX Georgetown South Corridor Noisewall Construction<br />
In 2014 Brennan Paving and Construction landed their first<br />
Metrolinx contract to construct new 5.0m high noise walls<br />
and security fencing along the Metrolinx railway corridor<br />
for the Union Pearson Express (UP Service). Project value<br />
of $87.3M<br />
The project runs <strong>with</strong>in the railway corridor from downtown<br />
Toronto at Strachan Avenue to the north limit of<br />
Hwy 27 (approximately 13 km/ 26km of fence line) and our<br />
contract is made of 8.7 km of Noisewall, 10 km of Security<br />
fence and 6 km of Chain link and Farm fence.<br />
Target completion for this project is June <strong>2015</strong> to be ahead<br />
of the Pan-Am games.<br />
The noise walls are designed, built, and supplied by Armtec, a leading international supplier of these systems.<br />
Ditching for sub-drain installation<br />
28 <strong>MILLER</strong> / McASPHALT NEWSLETTER <strong>2015</strong> EDITION<br />
<strong>MILLER</strong> / McASPHALT NEWSLETTER <strong>2015</strong> EDITION<br />
www.millergroup.ca<br />
www.mcasphalt.com<br />
29