FIJI Post-Disaster Needs Assessment<br />
Activity<br />
Responsible Agency<br />
Cost<br />
(F$ million)<br />
Professional development training of building inspectors MoIT/MoH/MLGHE 1.8<br />
House addressing system in affected cane farming areas MoS/ FSCL 0.2<br />
House addressing system in affected peri-urban informal settlements MLGHE/MoL/PCN 0.2<br />
Replace minimum household goods and school uniform (destroyed houses<br />
only)<br />
Prepare and pre-approve 4-6 'model' houses (one room starter that can be<br />
incrementally expanded over many years) with materials list and specifications<br />
for voluntary uptake by hhds<br />
Reconstruct 11,030 to starter house/core unit<br />
Reconstruct 11,030 to build back better standards<br />
Initial repairs to critical elements (partial roof) of major damage houses<br />
Initial repairs to critical elements (partial roof) of minor damage houses<br />
MOF/Individual Households/FNPF 53.8<br />
MoIT/MLGHE/MRMD&NDMO/<br />
HfHF/MTCT (Rotahomes)/FIE/MRH<br />
MoIT/MLGHE/MRMD/NDMO/<br />
Individual Households<br />
MoIT/MLGHE/MRMD/NDMO/<br />
Individual Households<br />
MoIT/MLGHE/MRMD/NDMO/<br />
Individual Households<br />
MoIT/MLGHE/MRMD/NDMO/<br />
Individual Households<br />
30,369 household repairs toolkit GoF with support from NGOs and<br />
Donors<br />
Prepare and pre-approve 2 wet area designs with materials lists and specs<br />
GoF with support from Development<br />
partners<br />
Reconstruct 11,030 water and shower units MoH/MRMD/NDMO/households 36.2<br />
Transportation to Viti Levu GoF 1.2<br />
Transportation to Vanua Levu GoF 1.2<br />
Transportation to Maritime islands GoF 1.0<br />
Source: Estimations by Assessment Team.<br />
Table 91: Recovery and Reconstruction Needs for Transport<br />
Activity<br />
Responsible Agency<br />
0.1<br />
77.2<br />
490.6<br />
26.9<br />
135.6<br />
13.2<br />
0.1<br />
Cost<br />
(F$ million)<br />
Total Recovery and Reconstruction Needs 177.9<br />
Recovery Needs 3.2<br />
Restoring full access and connectivity through affected road sections FRA 2.8<br />
Salvage grounded vessels Private sector 0.3<br />
Clear debris from runways and rebuild security fences AFL 0.05<br />
Reconstruction Needs 174.7<br />
Reconstruction of bridges, crossings, culverts, and approaches. Repair of<br />
associated facilities.<br />
FRA 131.2<br />
Reconstruction of rural jetties FRA 37.0<br />
Repair of aids to navigation MSAF 2.3<br />
Repair of port terminal buildings FPCL 0.8<br />
Repair of airport terminal buildings AFL 3.4<br />
Source: Estimations by Assessment Team.<br />
Tropical Cyclone Winston, February 20, 2016<br />