21.06.2017 Views

EDC 2014 SR (UPDATED)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>EDC</strong> <strong>2014</strong> Performance Report<br />

On November 12, <strong>2014</strong>, EBWPC received the DOE’s Certificate of Endorsement (COE) for FIT<br />

eligibility under docket number COE-FIT No. W-<strong>2014</strong>-11-002 endorsing the 150-MW Burgos<br />

Wind Project for the purpose of qualifying under the Feed-In Tariff (FIT) System.<br />

Total revenue recognized by the Burgos Wind Energy Project from November 11, <strong>2014</strong> to<br />

December 31, <strong>2014</strong> amounted to ₱188.3 million.<br />

Upon completion of the Burgos Wind Project, the Company transferred a total cost of<br />

₱16,241.2 million from the “Construction in Progress” account to completed property, plant and<br />

equipment under the “Power Plants” account. For the period from November 11, <strong>2014</strong> to<br />

December 31, <strong>2014</strong>, the depreciation expense recognized on the completed assets of Burgos Wind<br />

Project amounted to ₱133.1 million while the total revenue generated amounted to ₱188.3 million.<br />

Completion of the Northern Negros Geothermal Plant to Nasulo Geothermal Plant (N2N) Project<br />

In April 2011, <strong>EDC</strong> suspended the operations of its 49-MW Northern Negros Geothermal Plants<br />

(NNGP) because the plant was not capable of operating on its designed capacity due to steam<br />

supply limitations. In the last quarter of 2013, to utilize the facilities and fixed assets of NNGP,<br />

<strong>EDC</strong> transferred the components of the power plant of NNGP to Nasulo Power Plant which will<br />

be constructed site in Southern Negros. The N2N Project was implemented in two phases.<br />

Phase 1 covered the site preparation and civil works, including the construction of the powerhouse<br />

building and other civil structures and foundations while Phase 2 covered the relocation of the<br />

existing unit and electro-mechanical equipment from NNGP going to Nasulo.<br />

On July 21, <strong>2014</strong>, the Company declared that the Nasulo Power Plant achieving a capacity of<br />

49.4-MW was already complete and in the condition necessary for it to operate as intended by<br />

management. Upon completion of the Nasulo Power Plant, the adjacent Nasuji Power Plant with<br />

capacity of 20 MW has been placed on preservation mode.<br />

During the relocation and construction of the Nasulo Power Plant, the Company incurred general<br />

borrowings used to fund the project. In <strong>2014</strong>, the borrowing costs capitalized in connection with<br />

the project amounted to ₱14.4 million using capitalization rate of 6.3% per annum.<br />

The Company performed testing run from April <strong>2014</strong> to July 20, <strong>2014</strong>. The total revenue<br />

generated from testing amounted to ₱343.5 million. Out of this amount ₱99.8 million was offset<br />

against the costs of testing whether the assets are functioning properly.<br />

The total costs capitalized for the construction of the Nasulo Power Plant amounted to<br />

₱4,107.7 million, including assets came from NNGP. From July 21, <strong>2014</strong> to December 31, <strong>2014</strong>,<br />

the related depreciation expense recognized for the Nasulo Power Plant amounted to ₱65.9 million.<br />

Transfer of certain NNGP assets to Palinpinon Power Plant<br />

In February 2012, <strong>EDC</strong> transferred certain vacuum pumps previously used and located in NNGP to<br />

Palinpinon Power Plant located in Southern Negros and owned by GCGI. Since these transferred assets<br />

(which had been previously impaired in NNGP) can now be utilized and were included in the cashgenerating<br />

unit of the Palinpinon Power Plant, the Company recognized a corresponding reversal of<br />

impairment loss amounting to ₱63.6 million, representing the net book value of the assets transferred had<br />

no impairment loss been previously recognized. The reversal of impairment was recognized under NIGBU<br />

operating segment.<br />

Completion of the Rehabilitation of Bac-Man Geothermal Power Plants (BMGPP)<br />

On May 5, 2010, BGI acquired the 150 MW BMGPP in an auction conducted by PSALM where<br />

BGI submitted the highest offer price of US$28.3 million.<br />

199

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!