14.12.3 To complete a HAZOP the operations of the MASS unit must be broken down into individual sections or nodes<br />
and each node evaluated for potential issues and as such this should highlight the personnel skills required to<br />
deal with such operations.<br />
14.12.4 Figure 14-1 below shows an outline of the suggested procedure to conduct the HAZOP for each node. It is<br />
recommended that this is conducted in a multidiscipline workshop environment with input from all departments<br />
to ensure that all aspects of the MASS operations are considered. Using a multidiscipline team will also allow the<br />
operating company to outline how many of each operator can be expected to be required in the control room.<br />
The HAZOP results may form a component of the due diligence towards the makeup and manning of the<br />
operations team as a whole.<br />
Figure 14-1: Flow diagram to determine level of Operators Training<br />
OPERATION<br />
DEFINITION<br />
HAZARDS<br />
IDENTIFICATION<br />
FREQUENCY<br />
ANALYSIS<br />
CONSEQUENCE<br />
ANALYSIS<br />
CURRENT<br />
TRAINING LEVEL<br />
FURTHER TRAINING<br />
REQUIREMENTS<br />
DEVELOP TRAINING<br />
MATRIX<br />
RISK<br />
EVALUATION<br />
AS LOW AS<br />
REASONABLY POSSIBLE<br />
NO<br />
YES<br />
OPERATION<br />
ASSESSED<br />
110<br />
MASS UK Industry Conduct Principles and Code of Practice Version 7