With regard to the specific provisions of IFRIC 12, in Note<br />

2.2, letter b), the conclusion reached by the Company is<br />

described in detail. It consists of having to recognize an<br />

intangible asset for its right to charge the general public for<br />

use of the infrastructure it operates, considering that the total<br />

income obtained will depend on the volume of users that<br />

use the service, with no guaranteed minimum income.<br />

25.2 Characteristics of the Concession Contract<br />

1. The concession contract is comprised of the Bidding<br />

Conditions, the explanatory circulars, the decree of award,<br />

the Supplementary Agreements No. 1 and No. 2 , The Ad<br />

Referendum Agreements No. 1 and No. 2, MOP’s Supreme<br />

Decree No. 514 and the relevant provisions of the various<br />

laws summarized below:<br />

- MOP Supreme Decree 900 of 1996, which establishes the<br />

adapted, coordinated and standardized text of MOP Statutory<br />

Decree 164 of 1991, Law on Public Works Concessions.<br />

- MOP Supreme Decree 956 of 1997, Enabling Regulations<br />

of the Law on Public Works Concessions.<br />

- Article 87 of MOP Statutory Decree 850 of 1997, which<br />

establishes the adapted, coordinated and standardized<br />

text of the Basic Law on the Ministry of Public Works, Law<br />

15,840 of 1964, and Statutory Decree 206 of 1996, the<br />

Roadways Law.<br />

2. The concession is for 390 months as stipulated in<br />

the modification set forth in letter d) of number 6.2 of<br />

Supplementary Agreement No. 1, entered into on July 12,<br />

2007, which modified the Concessions Contract for the<br />

State-owned Public Works called “Concesión Variante<br />

Vespucio- El Salto – Kennedy”. Through this agreement<br />

the original term of the concession that had been set forth<br />

in article 1.7.6 of the Bidding Terms and Conditions was<br />

extended in six additional months. The start of the concession<br />

shall be computed pursuant to a set forth in article 1.7.5<br />

of the Bidding Terms and Conditions, that is from the date<br />

of publication Of the Supreme Decree of Award of the<br />

Concession Contract on the Official Gazette. The number of<br />

this decree is No. 1129 dated November 26, 2004, and was<br />

published on the Official Gazette on February 21, 2005.<br />

Consequently, the date of termination of the concession is<br />

August 21, 2037.<br />

3. The Concession Holder will repair, preserve, maintain<br />

and operate the works set forth in the Bidding Terms and<br />

Conditions, that is the concession project called “Variante<br />

Vespucio - El Salto - Kennedy” which will communicate<br />

Avenida Américo Vespucio in the area of El Salto, district<br />

of Huechuraba, with the districts of Providencia and Las<br />

Condes, on Avenida del Cerro and Avenida Kennedy<br />

respectively. The project will be materialized by way of the<br />

construction of two parallel tunnels that will cross through<br />

the <strong>San</strong> <strong>Cristóbal</strong> Hill and a set of surface roads that will<br />

make the connections referred to in number 1.3 of the<br />

Bidding Terms and Conditions.<br />

The Concession-holding Company prepared the necessary<br />

Detail Engineering Projects for the execution of the works<br />

referred to in article 1.9.1 of the Bidding Terms and<br />

Conditions, and may incorporate, at its own cost and under<br />

its own responsibility, with the consent of the State Inspector,<br />

other additional works in addition to those that are required<br />

as a minimum, that in the Concession-holding Company<br />

may contribute to improve the standards and indices set<br />

forth in the Bidding Terms and Conditions.<br />

The main works executed in the approximately 4.1 Km. of<br />

new road are:<br />

-Construction of approximately 2.2 Km of a one-way, two<br />

lane highway, 3.5 meters wide with variable-width median<br />

strips and 1.5 m shoulders.<br />

-Construction of two one-way tunnels approximately 1.9<br />

Km long.<br />

-Construction of Electronic Collection Gantries.<br />

-Connection to the Américo Vespucio - El Salto Crossover.<br />

-Avenida Kennedy- Lo Saldes Connection.<br />

-Avenida El Cerro Connection.<br />

The Concession includes the maintenance of all the works<br />

executed by the Company under conditions and standards<br />

stipulated in the Bidding Terms and Conditions for the Stages<br />

of Construction and Operation.<br />