03.03.2013 Views

A new face drilling rig for narrow tunnels and ... - Advanced Mining

A new face drilling rig for narrow tunnels and ... - Advanced Mining

A new face drilling rig for narrow tunnels and ... - Advanced Mining

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Going underground<br />

Experts have been predicting <strong>for</strong> years that the nonmetallic<br />

minerals industry would go underground. A few<br />

pits did take this step, usually <strong>for</strong> environmental reasons,<br />

i.e. to reduce the dust <strong>and</strong> noise nuisance <strong>for</strong> the local<br />

residents. This included our client Märker Kalk GmbH,<br />

whose resources at the Herrlingen quarry in Baden-<br />

Wuerttemberg were nearing exhaustion.<br />

There was no prospect of obtaining yet another approval<br />

<strong>for</strong> sur<strong>face</strong> quarrying close to a residential district. The<br />

logical move was to consider using underground mining<br />

methods <strong>and</strong> as a result the Mähringer Berg project was<br />

put into action.<br />

Planning considerations<br />

Planning considerations were based market conditions<br />

<strong>and</strong> the geology of the deposits ‘All is dark ahead of the<br />

pick’- this old mining saying had twofold significance when<br />

it came to the Märker project:<br />

It applied firstly to the client’s general project <strong>for</strong><br />

developing the underground workings <strong>and</strong> building a<br />

<strong>new</strong> kiln to process the high-grade white lime. This first<br />

required a lengthy planning <strong>and</strong> clarification process that<br />

included financing arrangements, technical equipment,<br />

licences <strong>and</strong> partners. All these procedures were carried<br />

out against a background of increasing dem<strong>and</strong> <strong>for</strong> the end<br />

product. But now that every - thing is ready <strong>for</strong> ‘harvesting’<br />

the market appears to be much less favourable. The global<br />

economic crisis, which has been accompanied by a fall in<br />

dem<strong>and</strong>, has left its traces. Nevertheless, as soon as the<br />

markets recover this long-term investment project will be<br />

delivering the expected returns.<br />

And secondly to the geology in the strict sense of the<br />

word. In 2001 an exploration roadway was driven <strong>and</strong> a<br />

small-scale test extraction undertaken. And the geology, it<br />

has to be said, was perfect.<br />

However, after the contract to develop the Mähringer<br />

Berg deposits was awarded in June 2007 to the Mähringer<br />

Berg joint venture, comprising Schachtbau Nordhausen<br />

GmbH <strong>and</strong> Thyssen Schachtbau GmbH, it was found that<br />

the geological conditions encountered along the 1,350 m<br />

of drivage differed somewhat from the o<strong>rig</strong>inal predictions<br />

<strong>and</strong> findings.<br />

Rockbolts, weldmesh panels <strong>and</strong> shotcrete had to be<br />

employed on a large scale in the long-term excavations<br />

Issue 04 | 2010<br />

TRANSFER OF TECHNOLOGY<br />

<strong>and</strong> roadways. However it is hoped that the poor geology<br />

encountered in some of the roadway developments will not<br />

be repeated to the same extent in the excavations made to<br />

the north of the same extraction zone.<br />

The ‘Mähringer Berg deposits’<br />

development project<br />

Excavation work on the conveyor road, parallel headings,<br />

crosscuts <strong>and</strong> rooms <strong>for</strong> the crusher, trans<strong>for</strong>mer <strong>and</strong> mine<br />

fan began on 09.09.2007. The highly karstified strata called<br />

<strong>for</strong> the highest safety st<strong>and</strong>ards <strong>and</strong> required a lot more<br />

support than had been planned. Roadways with profiles of<br />

32 to 36 m 2 would have to serve as the main production<br />

arteries <strong>for</strong> decades to come. The crusher room, <strong>for</strong><br />

example, was not spot-bolted but instead supported by a<br />

30 cm-thick coating of shotcrete, two layers of weldmesh<br />

<strong>and</strong> rockbolts up to 5 m in length. After each round of<br />

shots the heading team had to reassess the condition of<br />

the strata <strong>and</strong> determine in collaboration with client the<br />

most appropriate measures to be used <strong>for</strong> support <strong>and</strong><br />

rein<strong>for</strong>cement.<br />

In order not to contaminate the high-quality lime<br />

shotcreting was only permitted in the cut-through road.<br />

More than 3,000 tonnes of this material were eventually<br />

used in all the infrastructure cavities.<br />

The increased safety measures, additional length of<br />

drivages required <strong>for</strong> the parallel heading <strong>and</strong> crosscuts<br />

<strong>and</strong> the need <strong>for</strong> additional ripping at the roof <strong>and</strong> ancillary<br />

support work all combined to delay the completion of the<br />

project by nearly half a year.<br />

The development work was completed at the end<br />

of 2008. A total of 1,350 m of roadways <strong>and</strong> some<br />

49,000 m 3 of cavities had been excavated at an average pull<br />

of 3.14 m <strong>and</strong> with an explosives consumption rate of about<br />

1.7 kg/m 3 . Each complete pull took 18.5 hours to execute,<br />

including time <strong>for</strong> ancillary operations <strong>and</strong> unscheduled<br />

support <strong>and</strong> rein<strong>for</strong>cement work.<br />

The shotfiring pattern, length of pull <strong>and</strong> choice of<br />

explosive all had to be coordinated so as to maximise the<br />

heading per<strong>for</strong>mance, reduce the degradation rate <strong>and</strong><br />

keep the proportion of debris less than 20 mm in size below<br />

35 %. Of course this could not always be achieved in those<br />

karst joints that were filled with loam <strong>and</strong> silt. An upper<br />

limit had also been placed on the vibration levels due to<br />

blasting, with no firing permitted at all between ten in the<br />

evening <strong>and</strong> six in the morning.<br />

www.advanced-mining.com<br />

29

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!