Civil engineer guide to fighting positions, shelters, obstacles
Civil engineer guide to fighting positions, shelters, obstacles
Civil engineer guide to fighting positions, shelters, obstacles
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
AFH 10-222 Volume 14 1 August 2008 141<br />
Table A2.1. Material Thickness for Protection Against Explosions (50<br />
feet away).<br />
Thickness<br />
of<br />
Material<br />
(Inches)<br />
82<br />
mm<br />
Mortar Rocket HE Shell Bomb<br />
120<br />
mm<br />
122<br />
mm<br />
122<br />
mm<br />
152<br />
Mm<br />
100<br />
lbs<br />
250<br />
lbs<br />
500<br />
lbs<br />
1,000<br />
lbs<br />
Brick<br />
Masonry<br />
Non-<br />
4 6 6<br />
Solid Walls<br />
6 8 8 10 13 17<br />
reinforced<br />
Concrete<br />
4 5 5 5 6 8 10 15 18<br />
Reinforced<br />
Concrete<br />
3 4 4 4 5 7 9 12 15<br />
Lumber 8 12 12 12 14 15 18 24 30<br />
Structurally Supported Material<br />
Brick<br />
Rubble<br />
9 12 12 12 12 18 24 28 30<br />
Soil*<br />
Gravel and<br />
12 12 12 12 16 24 30 NR NR<br />
Crushed<br />
S<strong>to</strong>ne<br />
9 12 12 12<br />
Sandbags<br />
12 18 24 28 30<br />
Brick<br />
Rubble<br />
10 18 18 18 20 20 20 30 40<br />
Dry Clay*<br />
Gravel and<br />
10 18 18 18 20 30 40 40 50<br />
Small<br />
S<strong>to</strong>nes<br />
10 18 18 18 20 20 20 30 40<br />
Dry Sand* 8 16 16 16 18 30 30 40 40<br />
Loose Parapets<br />
Dry Clay* 12 20 20 20 30 36 48 60 NR<br />
Dry Sand* 10 18 18 18<br />
Snow<br />
24 24 36 36 48<br />
Tamped 60 60 60 60 60 NR NR NR NR<br />
Unpacked 60 60 60 60<br />
Notes<br />
60 NR NR NR NR<br />
* Double the thickness when material is wet<br />
NR = material is not recommended