AFH 10-222 Volume 14 1 August 2008 51<br />
2.5.7.4. Second Layer. After the first layer is complete, align the second<br />
layer as depicted in Figure 2.26. Seal both layers <strong>to</strong>gether using the geotextile<br />
flaps located at the bot<strong>to</strong>m of the second layer and use the plastic ties <strong>to</strong><br />
connect them. Uniformly fill the second layer as previously described.<br />
Figure 2.26. Second Layer – Single-Bay Fighting Position.<br />
2.5.7.5. Composite Panels. Align the 2- by 14-foot composite panels on <strong>to</strong>p<br />
of the second layer of earth-filled units along the vertical walls as shown in<br />
Figure 2.27.<br />
Figure 2.27. Composite Panels – Single-Bay Fighting Position.