Chapter ñ14 Final Report: <strong>Gudiyattam</strong> <strong>Municipal</strong>ity<br />

Operating Ratio 1.12 1.59 1.37<br />

Debt Service Ratio 32% 89% 66%<br />

Category 3<br />

Long Term (2009-10 to 2028-<br />

29)<br />

Operating Ratio 1.12 1.59 1.31<br />

Debt Service Ratio 13% 89% 49%<br />

Category 3<br />

Note : 1 ñ Financially Sound; 2 ñ Financially Fragile; 3 ñ Financially Insolvent<br />

It may be observed that the <strong>Municipal</strong>ity is financially very fragile both in the short<br />

term and long term. The <strong>Municipal</strong>ity is unable to bear the high operation &<br />

maintenance expenses and interest cost on borrowings resulting in operating ratio ><br />

1% and Debt Service Ratio > 30%.<br />

14.12 INFERENCE.<br />

The investment capacity of Gudiyatham <strong>Municipal</strong>ity on ëAs is Where Basisí works<br />

out to Rs. 3973 lacs.<br />

The investment capacity of Gudiyatham <strong>Municipal</strong>ity works to Nil in case of<br />

Scenario II (With Metur CWSS project) and Nil in case of Scenario III (Without<br />

Metur CWSS project).<br />

Thus it can be inferred that Gudiyatham <strong>Municipal</strong>ityís financial position is weak<br />

and is not in a position to undertake major projects like water supply<br />

improvements and underground by way of borrowings on account of high<br />

operation & maintenance expenses and interest cost.<br />

Based on the above, it can be concluded that the <strong>Municipal</strong>ity based on its<br />

financial position can undertake only smaller projects identified in the CCP as<br />

given below :<br />

S.No. Particulars Total Priority Funding By<br />

A Physical Infrastructure Facilities L : G : M<br />

I Bus Stand<br />

a) Construction of New Bus Stand 300.00 B 90:00:10<br />

II Street Lights<br />

a) Proposed new lights 40.00 A 100% ULB<br />

b) Retrofitting existing lights & energy saving devices 15.86 A ESCO<br />

B Social Infrastructure Facilities<br />

- 165 -<br />

Voyants Solutions Private Limited