Chapter ñ10 Final Report: <strong>Gudiyattam</strong> <strong>Municipal</strong>ity<br />
It is important to assess consumption at the consumer ends which will helpful for<br />
performance of production system and supply side. Installation of good consumer<br />
meters will be starting point of recovery of cost of production and supply. For the<br />
horizon year 2039, it requires Rs. 1.28 Crores.<br />
The exiting water supply system has not proper disinfection system. As of now,<br />
bleaching powder only is used as disinfectant, so the installation of chlorinatiors will<br />
therefore be an important to health aspect. It estimated cost of 45 lacs . The<br />
description of fund requirement for the water supply sector is given in the table 10.3:<br />
The mettur scheme has been identified for combined water supply scheme for this<br />
municipality. The schematic and proportionate cost details of mettur scheme is<br />
presented in the below figure 10.1.<br />
The water can be drawn from palar river upto intermediate stage 2024 and after<br />
intermediate stage the mettur scheme can be used. The capital cost of mettur<br />
scheme is Rs. 1170 crores and O&M cost is Rs 40 crores per annum. The proportionate<br />
capital cost of <strong>Gudiyattam</strong> municipality is Rs. 72.11 crores and O&M cost is Rs. 2.47<br />
crores.<br />
The total estimated cost including renovation of existing water supply scheme is Rs.<br />
8224.33 lacs.<br />
. - 91 -<br />