Oseberg D Offshore Platform: This project involves the design, manufacture and assembly of a heat<br />
recovery module for Statoil Hydro Norway in the North Sea. This project commenced in May 2008 and is<br />
scheduled to be completed in 2012. The delivery of the HRSG module, on free-on-board (“FOB”) basis, is<br />
scheduled to be in April 2010 The contract value of this project is €17.00 million.<br />
Petrochemical Plant: This project involves the design, manufacture and assembly of two crude oil firing<br />
industrial boilers for Saudi Kayan Petrochemical Company in Al-Jubail, Saudi Arabia. This project<br />
commenced in June 2007, the boilers have been delivered on FOB basis in June 2009 and the project is<br />
scheduled to be completed in 2011. The contract value of this project is €61.00 million.<br />
Cogeneration Plant: This project involves the design, manufacture and assembly of two HRSG with a fuel<br />
gas firing, ultra lox nox burners for Tractebel in Arles, France. This project commenced in March 2001 and<br />
was completed in December 2004. The contract value of this project was €5.00 million.<br />
The largest company in the Sofinter group is Ansaldo, which has a history of over 120 years and has supplied and<br />
installed over of 1,000 plants worldwide with capacity of more than 80,000 MW. Ansaldo specializes in the design,<br />
engineering, manufacture, supply, erection and commissioning of utility boilers and HRSGs. Ansaldo has a Benson<br />
license for once-through boilers (sub-critical, supercritical and ultra-supercritical boilers and once-through HRSGs.<br />
The current capacity of Ansaldo is approximately 2,500 MW per annum. In India, Ansaldo is qualified in the first<br />
round for the supply of supercritical size boilers by the Government.<br />
Some selected ongoing major projects undertaken by Ansaldo are set forth below:<br />
Torrevaldaliga Nord Project: This project involves the engineering, manufacturing, supply, erection and<br />
start-up of three coal fired, once-through supercritical boilers for Enel S.p.A in Torrevaldaliga North, Italy.<br />
The contract was awarded in December 2004 and the first unit was completed in June 2009, with the second<br />
unit and the third unit scheduled to be completed by January 2010 and June 2010, respectively. Ansaldo’s<br />
share of the value of this project is €310.00 million, with the residual value (as at June 30, 2009) being<br />
€14.00 million.<br />
Shuaibah Project: This project involves the engineering, manufacturing, supply , erection and start-up of<br />
three oil fired boilers (including electrostatic precipitators) for Shuaibah Water & Electricity Company in<br />
Shuaibah, Saudi Arabia. The contract was awarded in January 2006. The provisional acceptance certificate<br />
of the whole plant, which indicates completion of the project, is expected to be received by December 2009.<br />
Ansaldo’s share of value of this project is €211.00 million, with the residual value (as at June 30, 2009)<br />
being €2.00 million.<br />
Abu Qir Project: This project involves the engineering, manufacturing, supply, erection and start-up of two<br />
gas and mazut oil fired boilers for West Delta Electricity Production Company in Abu Qir, Egypt. The<br />
contract was awarded in September 2008. The first unit is scheduled to be completed in April 2012 and the<br />
second unit is scheduled to be completed in August 2012. The contract value for the offshore portion, of<br />
which Ansaldo is in charge, is €188.00 million and that for the total on-shore portion, of which Ansaldo<br />
Caldaie Boiler Egypt (98.00% owned by Ansaldo) is in charge, is EGP377.75 million. As at June 30, 2009,<br />
the residual off-shore portion value was €134.00 million and the residual on-shore portion value was<br />
EGP289.85 million.<br />
El Tebbin Project: This project involves the engineering, manufacturing, supply, erection and start-up of<br />
two gas and oil fired boilers for Cairo Electricity Production Company in El Tebbin, Egypt. The contract<br />
was awarded in May 2007 and the project is scheduled to be completed by July 2010. The contract value for<br />
the offshore portion, of which Ansaldo is in charge, is €102.00 million and that for the total on-shore<br />
portion, of which Ansaldo Caldaie Boiler Egypt (98.00% owned by Ansaldo) is in charge, is EGP147.79<br />
million. As at June 30, 2009, the residual off-shore portion value was €30.00 million and the residual onshore<br />
portion value was EGP80.00 million.<br />