Indonesia<br />

<strong>The</strong> accelerated electricity development programme consists of several different<br />

types of power plant: 4.3GW steam power, 3.6GW geothermal power, 1.6GW steam gas<br />

power, <strong>and</strong> 1.2GW micro hydro power.<br />

<strong>The</strong> total number of power plants currently being developed by PT PLN <strong>and</strong><br />

IPPs is equivalent to 29.4GW. <strong>The</strong> 10GW second-phase acceleration programme should<br />

continue the 10GW first-phase programme so it can cope with an average annual<br />

electricity dem<strong>and</strong> growth of around 7 per cent.<br />

Further, Presidential <strong>Regulation</strong> No. 13 of 2010 provides support for publicprivate<br />

participation by establishing PT Sarana Multi Infrastruktur <strong>and</strong> its subsidiary PT<br />

Infrastruktur Financing, to play the role of a fund to support infrastructure financing.<br />

<strong>The</strong> government also supported the electricity industry by establishing PT Penjaminan<br />

Infrastruktur Indonesia to provide guarantees for infrastructure projects, including in<br />

the electricity sector.<br />

During the past 12 months regulations issued by the MEMR have been geared<br />

to support the use of gas <strong>and</strong> geothermal energy as sources of power generation. <strong>The</strong>se<br />

regulations cover the price of electricity from geothermal power plants, allocation of gas<br />

for power plants, <strong>and</strong> supporting geothermal power plant developments based on the<br />

second acceleration programme in power plant development.<br />

VII<br />

CONCLUSIONS <strong>and</strong> OUTLOOK<br />

<strong>The</strong> 2006–2025 National <strong>Energy</strong> Policy, the <strong>Energy</strong> Blueprint 2008–2027, <strong>and</strong> the<br />

laws governing electricity, oil <strong>and</strong> gas <strong>and</strong> mining will need to have detailed guidelines<br />

<strong>and</strong> action plans – such as strict energy performance st<strong>and</strong>ards <strong>and</strong> financial incentive<br />

schemes – to ensure successful implementation.<br />

A further step towards ensuring a secure <strong>and</strong> sustainable energy sector would<br />

be for Indonesia to continue its policy of reducing fossil fuel subsidies <strong>and</strong> shift them<br />

towards green subsidies. <strong>The</strong> government’s effort to shift its energy policy is being<br />

implemented through policies that support private investors in the energy sectors<br />

<strong>and</strong> working together on a bilateral level as well as with private agencies to prepare a<br />

sustainable working environment. Securing domestic supply of fuel for power generation<br />

<strong>and</strong> providing a mechanism for risk allocations for investment show a trend towards<br />

supporting the market in terms of legal framework.<br />

Although the government has the necessary ministries <strong>and</strong> agencies in place for<br />

effective energy policymaking <strong>and</strong> implementation, the coordination, decision making<br />

<strong>and</strong> overlapping or unclear division of responsibilities among these institutions remain<br />

serious issues. Complication also stems from the decentralisation of some administration<br />

to the regional governments.<br />

Delays on progress in projects already in the pipeline may occur due to the 2014<br />

Presidential Election.<br />