Turkey<br />

c<br />

d<br />

e<br />

the requested connection has a preventive impact on TEİAŞ or a distribution<br />

company’s public service obligations (this must be evidenced by TEİAŞ or the<br />

distribution company);<br />

the facility will cause a decrease in the electricity quality of the system; or<br />

with respect to wind <strong>and</strong> solar facilities, there is an alternative connection point<br />

that is more economical <strong>and</strong> efficient.<br />

Furthermore, once connected to the system, if there is a need for a system usage capacity<br />

increase or a new investment <strong>and</strong> there is insufficient financing for such an investment,<br />

then third parties requiring the connection may make the necessary investment in<br />

accordance with any required st<strong>and</strong>ards on behalf of TEİAŞ or the distribution company.<br />

In such circumstances, the total investment amount may be set off from the system usage<br />

fees or distribution tariffs under the connection agreement that will be executed between<br />

the parties.<br />

Last, it should be noted that TEİAŞ or the distribution company must give<br />

priority to those facilities with renewable energy sources <strong>and</strong> facilities with indigenous<br />

natural resources.<br />

ii Tariffs<br />

EMRA creates the principles <strong>and</strong> procedures for setting certain tariffs, <strong>and</strong> it reviews <strong>and</strong><br />

approves the methodologies <strong>and</strong> tariffs submitted by certain other authorities. Article<br />

13 of the EML <strong>and</strong> the Electricity Market Tariff <strong>Regulation</strong> set out the criteria for the<br />

preparation of tariff proposals by TEİAS, TETAŞ <strong>and</strong> other entities. Generally, tariffs<br />

must be cost-effective <strong>and</strong> are created ex ante according to a pre-defined methodology.<br />

Once they have been approved they are published in the Official Gazette <strong>and</strong> on EMRA’s<br />

website to ensure transparency. Broadly speaking, there are eight categories of tariffs:<br />

connection, transmission, distribution, average wholesale price, wholesale price for<br />

TETAŞ, retail supply, retail supply services <strong>and</strong> ancillary services.<br />

Also, as described below, Turkey has passed laws with respect to renewable energy,<br />

which provide incentives <strong>and</strong> benefits for renewable energy projects, including feed-in<br />

tariffs. <strong>The</strong>se tariffs are applicable to entities holding generation licences that started<br />

operation between 31 December 2005 <strong>and</strong> 18 May 2008, <strong>and</strong> lasts for 10 years from the<br />

date of operation.<br />

iii Supply security<br />

<strong>The</strong> MENR is responsible for monitoring the security of the electricity supply <strong>and</strong> for<br />

taking measures to protect it. In 2008, the EML was amended to ensure the security<br />

of the electricity supply <strong>and</strong> to provide new measures to prevent a supply deficit. For<br />

example, it increased the powers of MENR so that it is authorised to take any measure<br />

to secure the supply of electricity. Also, it is tasked with preparing a report on electricity<br />

security for each fiscal year. Moreover, it may announce a tender if energy investments<br />

are insufficient to meet dem<strong>and</strong>.<br />

In addition to increasing the authority of the MENR, the 2008 EML amendment<br />

also made TEİAŞ responsible for ensuring the reliability of the grid. While doing so,<br />

TEİAŞ must meet third-party dem<strong>and</strong>s for connection to the network <strong>and</strong> system use on<br />

294