Chapter 20<br />

South Africa<br />

Shamilah Grimwood <strong>and</strong> Zahra Omar 1<br />

I<br />

OVERVIEW<br />

i Electricity<br />

South Africa has a gross installed electricity generation capacity of about 36GW<br />

dominated by coal-fired electricity generation facilities (90 per cent). Electricity<br />

production from hydro, natural gas <strong>and</strong> oil sources located in South Africa is nominal<br />

(about 1 per cent). Nuclear electricity production (from the Koeberg power station,<br />

South Africa’s only nuclear power station) is estimated at 5 per cent, with South Africa<br />

importing the balance of its electricity consumption requirements mainly from the<br />

Cahora Bassa hydro-power plant in Mozambique <strong>and</strong> otherwise through the regional<br />

power exchange among members of the Southern African Power Pool. South Africa has<br />

over 400,000 kilometres of distribution network infrastructure plus 26,225 kilometres<br />

of transmission lines with a nominal voltage above 132kV. Its network infrastructure<br />

with a nominal voltage of 132kV or less comprises its distribution asset base.<br />

In March 2011, Eskom Holdings SOC Limited (‘Eskom’), 2 the national electricity<br />

supply utility, reported that South Africa’s reserve margin had improved to 14.9 per cent<br />

(up from 5 per cent in January 2008 when South Africa experienced severe blackouts<br />

reportedly due to constraints in coal supply <strong>and</strong> technical outages). South Africa’s current<br />

20-year new generation capacity plan proposes to more than double its installed capacity<br />

by 2030 by adding nearly 53GW. <strong>The</strong> generation mix of the proposed new generation<br />

capacity plan allocates 16.3GW for coal, 9.6GW for nuclear, 17.8GW for renewables<br />

<strong>and</strong> 8.9GW for other generation sources.<br />

1 Shamilah Grimwood is a partner <strong>and</strong> Zahra Omar is a senior associate at White & Case LLP<br />

(South Africa).<br />

2 Established in terms of the Eskom Conversion Act 3 of 2001.<br />

237