JI project participants AIE JISC<br />

Select and contract an AIE.<br />

Submit the PDD to the AIE.<br />

Make publicly available the PDD<br />

and receive comments on the<br />

PDD and any supporting information<br />

from Parties, stakeholders<br />

and UNFCCC accredited<br />

observers for 30 days.<br />

Make a determination based on<br />

paragraph 33 of the JI guidelines<br />

(corresponds to validation under<br />

the CDM).<br />

If a Party involved in the project<br />

activity or at least 3 members of<br />

the JISC request a review, the<br />

JISC shall:<br />

(a) Finalizes the review no later<br />

than 6 months or at the<br />

second meeting following the<br />

request for review;<br />

(b) Communicate its decision on<br />

the determination and the<br />

reasons for it to the project<br />

participants and the public.<br />

Its decision shall be final.<br />

Submit a report in accordance<br />

with the monitoring plan. The<br />

report shall be made publicly<br />

available.<br />

Make the determination publicly<br />

available, including a summary of<br />

comments received and a report<br />

of how due account was taken of<br />

these.<br />

No request for<br />

review is made<br />

The determination shall be<br />

deemed final 45 days after the<br />

date on which the determination<br />

is made public.<br />

Make a determination based on<br />

paragraph 37 of the JI guidelines<br />

(corresponds to verification<br />

under the CDM).<br />

If a request for<br />

review is made<br />

If a Party involved in the project<br />

or 3 members of the JISC<br />

request a review, the JISC shall:<br />

(a) At its next meeting or no later<br />

than 30 days after the formal<br />

request for the review decide<br />

whether to perform a review;<br />

(b) Complete its review within 30<br />

days following its decision to<br />

perform the review;<br />

(c) Inform the project participants<br />

of the outcome of the review,<br />

and make public its decision<br />

and the reasons for it.<br />

Make the determination publicly<br />

available, together with an explanation<br />

of its reasons.<br />

No request for<br />

review is made<br />

The determination shall be<br />

deemed final 15 days after the<br />

date on which the determination<br />

is made public.<br />

If a request for<br />

review is made<br />

Figure 4-3 Verification procedure under the JISC (Track 2 procedure)<br />

for the first 15,000 tonnes of CO 2 equivalent generated by the project in question in a given<br />

calendar year;<br />

(b) USD 0.20 per tonne of CO 2 equivalent of emission reductions or enhancements of removals for<br />

any amount in excess of 15,000 tonnes of CO 2 equivalent generated by the project in question<br />

in a given calendar year.<br />

(3) Advance payment (similar to registration fee under the CDM)<br />

(a) A fee equivalent to the expected average annual generation of emission reductions or<br />