JI project participants AIE JISC<br />
Select and contract an AIE.<br />
Submit the PDD to the AIE.<br />
Make publicly available the PDD<br />
and receive comments on the<br />
PDD and any supporting information<br />
from Parties, stakeholders<br />
and UNFCCC accredited<br />
observers for 30 days.<br />
Make a determination based on<br />
paragraph 33 of the JI guidelines<br />
(corresponds to validation under<br />
the CDM).<br />
If a Party involved in the project<br />
activity or at least 3 members of<br />
the JISC request a review, the<br />
JISC shall:<br />
(a) Finalizes the review no later<br />
than 6 months or at the<br />
second meeting following the<br />
request for review;<br />
(b) Communicate its decision on<br />
the determination and the<br />
reasons for it to the project<br />
participants and the public.<br />
Its decision shall be final.<br />
Submit a report in accordance<br />
with the monitoring plan. The<br />
report shall be made publicly<br />
available.<br />
Make the determination publicly<br />
available, including a summary of<br />
comments received and a report<br />
of how due account was taken of<br />
these.<br />
No request for<br />
review is made<br />
The determination shall be<br />
deemed final 45 days after the<br />
date on which the determination<br />
is made public.<br />
Make a determination based on<br />
paragraph 37 of the JI guidelines<br />
(corresponds to verification<br />
under the CDM).<br />
If a request for<br />
review is made<br />
If a Party involved in the project<br />
or 3 members of the JISC<br />
request a review, the JISC shall:<br />
(a) At its next meeting or no later<br />
than 30 days after the formal<br />
request for the review decide<br />
whether to perform a review;<br />
(b) Complete its review within 30<br />
days following its decision to<br />
perform the review;<br />
(c) Inform the project participants<br />
of the outcome of the review,<br />
and make public its decision<br />
and the reasons for it.<br />
Make the determination publicly<br />
available, together with an explanation<br />
of its reasons.<br />
No request for<br />
review is made<br />
The determination shall be<br />
deemed final 15 days after the<br />
date on which the determination<br />
is made public.<br />
If a request for<br />
review is made<br />
Figure 4-3 Verification procedure under the JISC (Track 2 procedure)<br />
for the first 15,000 tonnes of CO 2 equivalent generated by the project in question in a given<br />
calendar year;<br />
(b) USD 0.20 per tonne of CO 2 equivalent of emission reductions or enhancements of removals for<br />
any amount in excess of 15,000 tonnes of CO 2 equivalent generated by the project in question<br />
in a given calendar year.<br />
(3) Advance payment (similar to registration fee under the CDM)<br />
(a) A fee equivalent to the expected average annual generation of emission reductions or<br />