Management Report of the Board of Directors - Financial Year 2008<br />
Even so, for Portuguese companies to gain access to the<br />
large-scale reconstruction projects that are starting now, it is<br />
still considered essential to increase the level of cultural<br />
affinity between the peoples of Portugal and Angola, an area<br />
in which Portugal has a competitive advantage over all the<br />
other bidding countries.<br />
performance was again affected by the severe weather<br />
conditions of the region, with floods and overflows repeatedly<br />
interrupting the operations, but, despite everything, the<br />
contract job will be completed within the set deadlines.<br />
- ALGERIA<br />
In 2008, the installed productive capacity reached its maturity<br />
with several fully operating construction yards and only<br />
administrative setbacks prevented the good performance of<br />
the activity from being totally reflected in the reported profit<br />
volume.<br />
The works in the “2 ème Rocade Autoroutiere D’Alger Sur”<br />
carried out to fulfil the schedule of inaugurations foreseen for<br />
the current year.<br />
65 ONID / El Harrach - Execution of Diversion Works and Transfer El Harrach-Douera for the<br />
development of the Mitidja Centre Perimeter<br />
The contract job “MAO – Projet de Adduction du Couloir<br />
Mostaganem-Arzew-Oran – LOT 3.1” – for “ANBT – Agence<br />
Nationale de Barrages et Transferts”, has progressed so well<br />
that it will be possible to inaugurate its fundamental parts in<br />
the first quarter of the current year and achieve its full<br />
commissioning by the end of the current semester.<br />
64 2 nd Highway ring road of Alger-South<br />
The contract job “El Oued – Assainissement des Eaux<br />
Résiduaires Pluviales et Lutte Contre La Remontée de La<br />
Nappe Phréatique de La Vallée D’el Oued (Tranche 2)”, for<br />
“ONA – Office National de L´Assainissement”, continues at an<br />
excellent pace.<br />
66 ANBT / MAO - Mostaganem-Arzew-Oran Corridor Adduction Project - LOT 3.1<br />
In the works of “El Harrach – Réalisation des Ouvrages de<br />
Dérivation et Transfert El Harrach-Douera Pour L’<br />
Aménagement du Périmetre de La Mitidja Centre” – for<br />
“ONID – Office Nationale de Irrigation et Drainage”,<br />
In 2009, the railway works of Thenia - Tizou Ouzou were<br />
handed over and the contract job for the reconstruction of the<br />
Tindouf Air Base was awarded, while Teixeira Duarte<br />