-106-such as iron ore, on two of the three legs, the spread between the RFR of’the steel and <strong>aluminum</strong> ships would be reduced.In an ef<strong>for</strong>t to evaluate these factors, an optimistic <strong>aluminum</strong> shipmodel has been established incorporating the following changes:(a)(b)(c)(d)(e)The 2S per cent labor differential has been eliminated.One-half of the 43s ton fatigue allowance has been eliminated.The 100 ton abrasion.allowance on the tank top and wing bulkheadshas been eliminated.Fire protection <strong>for</strong> the deckhouse has been modified per ItemS previously discussed.A three leg voyage with weight-sensitive cargoes carried on.two legs over distamces of 4000, 84OO and 12,000 miles havebeen assumed, with ship life of 20, 25 and 30 years, to beconsistent with previous studies (Table 28).The reduction in first cost of the ship is $1,600,000 <strong>for</strong> singleship procurement, and the available deadwight has been increased by 360tons ● Thus the 7-1/2 per cent increase in available deadweight of the baselineship increases to about 8-1/2 per cent.The three-leg voyages were considered with the following assumptions:oRound voyage distances, ship life and number of shipspurchased are identical to the figures of Table 28.0 Average Annual Costs <strong>for</strong> all items which do not vary withacquisition cost are identical to the two-leg voyage.This may not be entirely accurate with regard to such itemsas fuel costs but it is felt that this discrepancy will notmaterially affect the final results.oSince cargo is carried on two of three legs instead of one oftwo legs, annual cargo carried will increase by 33 per centover the values listed in Table’28.0 An additional increase of 1 per cent <strong>for</strong> cargo carried overthe two leg voyage as listed in Table 28 was assigned to the<strong>aluminum</strong> vessel because of increased cargo deadweight due tothe reductions in lightship.ooSalvage value of the <strong>aluminum</strong> vessel was reduced directly inproportion to changes in material weight of the vessel asoriginally conceived+Owners Investment costs, i.e., non-depreciable costs in.curred during construction, were assumed independent ofacquisition costs.As indicated in Table 29 and Figure 23, the steel bulk carrier haslower RFR’s than,the <strong>aluminum</strong> ship <strong>for</strong> equal life spans, even <strong>for</strong> thishighly optimistic case.
TABLE 29 Comparison of Steel and Aluminum BulkCarriers ( C?za2Zenger Class) Three-Leg VoyagesCaseNumber<strong>Ship</strong> Life(Years)No. of <strong>Ship</strong>sPurchasedStrictureMaterialRound VoyageDistanceAnnual cargo&rried-L.T.RequiredF&eight RateWhip NetInvestment55)56)57)58)59)60)61)6z}63)64)65)66)67)68)69j70)71)72)20202025252530;;2020202525253030301steelSteelSteelSteelSteelSteelSteelSteelSteelAluminumAluminumAluminumAluminumAluminumAluminumAluminumAluminumAluminum4,0008,40012,0004,goo8,&0012,0004,0008,40012,000:,;:12;9004,0008,40012,0004,0008,40012,0001,338,460690,981483,6011,254,806679,0h2482,3911,?54,806679,042b82, 3911,447,155738,87352S,6U~,447,765738,873525,6hb1,447,?85738,873525,644$2.63 per ton5.127.172●434.746.6b2.3I4.486.272.68;.;:2:63;.;;2:625.067.10$14,520,406$14,520,4c6$14,520,1K36$14,745,466$!4,745,466$14,7M,466$14,745,466$14,745,466$111,745,466$16,1J67,612$16,467,612$16,467,612$?6,667,612$16,667,612$16,667,612$16,667,612$16,667,612$16,667,6?2* ship price + merfs Invest. Costs - Salvage Value
- Page 5:
CONTENTSI.. II.III.Iv.v.VI ●VII.I
- Page 9 and 10:
LIST OF FIGURES(Cent’d)FIGURE NO.
- Page 11 and 12:
I. INTRODUCTIONThis report summariz
- Page 13:
art in fabricating and maintaining
- Page 16 and 17:
MONTEROSSO GRANA /17VALGRANA / CARA
- Page 18 and 19:
-8-Numerous references have been re
- Page 20 and 21:
.10.TABLE 2. Mechanical Properties
- Page 22 and 23:
TABLE 2 Mechanical Properties of Al
- Page 24 and 25:
TABLE 3 Mechanical Property Limits
- Page 26 and 27:
-16-l?igures5, 6, 7 ati 8 present f
- Page 28 and 29:
-18-ti-’”’-”-””””-L
- Page 30 and 31:
-20-60 .r---.— ..,.— -——,L-
- Page 32 and 33:
.22-each stress level, rate of load
- Page 34 and 35:
-24-!Z456-H321 = 0.485083-H321 = 0.
- Page 36 and 37:
-26-(c)Members with partial or cont
- Page 38 and 39:
-28-AllOyS 5083 and 54.56(~ content
- Page 40 and 41:
-30-The previous paragraphs have de
- Page 42 and 43:
-32-The problem of cargo hold abras
- Page 44 and 45:
-34-The question of residual stress
- Page 46 and 47:
.36-Each alloy was given a relative
- Page 48 and 49:
-38-GENERAL OBSERVATIONSFYior to a
- Page 50 and 51:
-40-The question of comparative imp
- Page 52 and 53:
-42-(d)(e)Poor quality welds due to
- Page 54 and 55:
-44-The ABS criteria noted above we
- Page 56 and 57:
-46-DNV would consider fatigue in e
- Page 58 and 59:
-48-is less, for the exposed side s
- Page 60 and 61:
Equation (2):-50-Hu1l SMa~um = Hull
- Page 62 and 63:
-52-Another aspect of vibrations wh
- Page 64 and 65:
-54-000000000Bottom Shell PlateSide
- Page 66 and 67: -56-at the deck and keel. This stre
- Page 68 and 69: -58-AT is the change inUT= Thermal
- Page 70 and 71: -60-SUl@!ARYAll parties contacted f
- Page 72 and 73: -62-(c)(d)(e)(f)T~e exterior side o
- Page 74 and 75: TABLE 12 Aluminum Bulk Carrier - Su
- Page 76 and 77: .66-INSUT.ATION AND SHEATHINGShell8
- Page 78 and 79: -68-(b)(c)(d)(e)(f)(g)(h)(i)(j)At l
- Page 80 and 81: -70-IIF.INSTALLATION OF SYSTEMS AND
- Page 82 and 83: Rudder Assembly -carrier should be
- Page 84 and 85: -74-(b)MechanicalTensile Strength 6
- Page 86 and 87: -76-(e)The steel piping must be of
- Page 88 and 89: -78-Other Piping Systems and Valves
- Page 90 and 91: -80-struetion for the aluminum hull
- Page 92 and 93: -82-Large heavy type machine~ must
- Page 94 and 95: suffers attack in an alkaline envir
- Page 96 and 97: -86-REPAIRSObtaining proper repairs
- Page 98 and 99: -88-The design of the midship s~cti
- Page 100 and 101: -90-assuming the increase is applic
- Page 102 and 103: LIGHT SHIP WEIGHT ESTIMATE-92-In or
- Page 104 and 105: -94-TABLE 20 Aluminum Bulk Carrier
- Page 106 and 107: TABLE 22 Trim and StabilityFull Loa
- Page 108 and 109: -98-TABLE 24 Price of Steel Bulk Ca
- Page 110 and 111: GaseNumber. . . -.,- .TABLE 27 Comp
- Page 112 and 113: -1o2-TABLE 28CarriersComparison of
- Page 114 and 115: 12 ---n..T.[T7%l,=LEGS IU ORF=ErY
- Page 118 and 119: -108-7)is,zg~ gg~5e mzz~E’4E!~K2j
- Page 120 and 121: -11o-(a)(b)(c)(d)Inerting system fo
- Page 122 and 123: -112-fatigue, particularly in the p
- Page 124 and 125: -114-2k* Installation of Systems an
- Page 126 and 127: -116-LIST OF REFERENCES(7)Fatigue P
- Page 128 and 129: -11.8-LLST OF REFERENCES(Cent’d)(
- Page 130 and 131: -120-ADDITIONAL SOURCES OF INFORMAT
- Page 132 and 133: -122-redistribution of the still wa
- Page 134 and 135: -124-APPENDIX BEXCERPTS FROMRULES A
- Page 136 and 137: -126-92.07-10(d)(~) Interior stairs
- Page 138 and 139: -128-~gE1+0102030- .. ..—405060
- Page 140 and 141: ectintyclassification4KEYWORDSROLEL
- Page 142: SHIP STRUCTURE COMMITTEE PUBLICATIO